CONSTRUCT





        C1 Shopfront and BWIC






       C1.1 Hoardings

                                                                       under review
       All  hoardings  must  be  fit  for  purpose,  secure,   http://www.herasreadyfence.co.uk/
       tidy, allow adequate working  space and                readyhoard-on-ground.aspx or bespoke timber
       maintained in this manner  throughout  any             construction
       period of building work and weather conditions.
       Hoarding arrangements will be the contractors          McDonald’s have a number  of  approved
       choice, using either a heras on ground  solid          graphic  banners  available.  The  numbers  must
       panel system:                                          be  agreed  for  each  site  and  ordered  by the
                                                              contractor.






























































        C1.1           Hoardings                            2.0                        08 February 2014