CONSTRUCT
C3 Shopfitting
C3.20 Counter Ceiling Raft; Adaptations
Where the menu boards are installed using The new downstand will generally be a MDF box,
a ceiling mounted cradle (or if it is impossible 200mm deep, projecting 118mm from the face
to locate on the menu board bulkhead) then of the existing raft. The exception to this sectional
the ORB should located within a new, add on detail occurs to suit the ORB as identified.
section to the counter ceiling raft.
The full new downstand and existing counter
A new MDF downstand will be bolted to the ceiling raft should be redecorated white
front face of the existing MDF counter raft as throughout.
identified in the following details. It is imperative
that the principal contractor check the existing
unistrut suspension system and confirm or
upgrade this to suit the additional weight being
added.