Page 4 - B8773-AEW-XX-XX-PP-A-0001_[P4]_Contractors Manual
P. 4

The Contractor





                            D R A F T




       Will be responsible for and will be deemed to         It is one of the standard DP UK&I Ltd conditions
       have included in their price for:                     that the shopfitting company acts as “Principal
       •  undertaking  role  of  Prinicple  Contractor  in   (Main) contractor”. As such it is the shopfitter’s
          accordance with the CDM Regulations 2015           responsibility to  contact  ALL  other  suppliers
       •  undertaking construction phase under CDM           and contractors and ensure that their delivery
          Regulations                                        and/or  installation  dates  are  arranged  and
       •  preparing  construction  phase  Health  and        confirmed to suit the shopfitter’s programme.
          Saftey plan prior to commencement of the
          works                                              However, it is the main contractor’s responsibility
       •  liasing  with  Building  Control/  Approved        to  ensure  all facilities  are  in place to  enable
          Inspector,  ensuring  all  works  comply  with     others to complete their works on the appointed
          building control and fire officer                  days i.e. electrical works advanced enough to
       •  coordinating  with  the  statutory  services       allow phone installation, etc.
          providor  and  integrating  service  providers’
          work  into  the  construction  programme,          Where  appropriate,  the  Principal  Contractor
          providing attendence where necessary               is issued with  a  copy  of  the  Domino’s
       •  undertaking  detailed  setting-out  survey         purchase order schedule with contact details.
          prior to commencing manufacture or fit-out         Other  suppliers  are  normally  given  a  “week
          and  advising  the  PM/  Design  Team  of  any     commencing”  delivery  date.  The  Principal
          significant variances                              Contractor must therefore plan the works and
       •  coordinating  with  and  integrating  into  the    make arrangments for specific dates as required.
          construction  programme,  delivery  and            Be aware that some suppliers have significant
          setting out of items supplied by others            lead times. DO NOT expect immediate delivery.
       •  providing comprehensive Health and Saftey          If there are any problems with cooperation and
          file on completion of the works incorporating      availability from suppliers, the Employer should
          the Opetation and Maintenance manual               be advised as soon as possible.
       •  responsibility for the security of the site and
          insurance of works during the contract             If site events require a change to a previously
       •  delivering  the  finished  project  within  the    booked  date,  the  Principal  Contractor  MUST
          programme  instruction  from  the  employer        rearrange, providing as much notice as possible.
          to  proceed  with  the  works,  including  price   Charges for abortive visits due site conditions, will
          for necessary out of hours, or weekend work        be charged back to the Principal Contractor.
       •  acting as the keyholder for the duration of the
          works  and  to  make  suitable  arrangements       The  Principal  Contractor  must  prepare  and
          so access to the premises is available at all      issue  a  detailed  construction  programme
          times in the event of emergencies                  highlighting tasks, deliveries and critical dates to
                                                             the Employer/ Project Manager before starting
                                                             on site. Deviations from the programme must be
                                                             reported immediatley.
   1   2   3   4   5   6   7   8   9