TYPICAL 10-15 DAY WORK PROCESS







                    Week 1-2                                                                           Week 2-3



            Remove flat roof/Insulate flat roof                                     Fit new Window/Door


            Remove Garage Door                                                      Skim coat plaster

            Infill opening
                                                                                    2 nd  Fix Electrics

            1 Fix Electrics                                                         (to current part P standards)
              st
            (to current part P standards)
                                                                                    2 nd  Fix Tiling (if required)
            1 Fix Plumbing (if required)
              st
                                                                                    2 nd  Fix Plumbing (if required)
            Create floating/suspended flooring

                                                                                    2 nd  Fix Carpentry
            Insulate external walls


            Plasterboard walls and ceilings                                         Rectify any Snags



              This is only an estimation of timescales, as each conversion will be independently
                                                   scheduled for work before we start.