TYPICAL 10-15 DAY WORK PROCESS
Week 1-2 Week 2-3
Remove flat roof/Insulate flat roof Fit new Window/Door
Remove Garage Door Skim coat plaster
Infill opening
2 nd Fix Electrics
1 Fix Electrics (to current part P standards)
st
(to current part P standards)
2 nd Fix Tiling (if required)
1 Fix Plumbing (if required)
st
2 nd Fix Plumbing (if required)
Create floating/suspended flooring
2 nd Fix Carpentry
Insulate external walls
Plasterboard walls and ceilings Rectify any Snags
This is only an estimation of timescales, as each conversion will be independently
scheduled for work before we start.