Page 4 - White Estimate
P. 4

Estimate #
                                                                                                                  prelim
   Name / Address
   Emily and Dean White                                                                                           Date
   2362 New Jersey Ave
   San Jose CA 95124                                 ESTIMATE                                                    5/8/2017


   #    item            Description                                                                              Total
                        GENERAL CONDITIONS
   1    Plans/Architect  by owners / provide 3 hardcopies and pdf files to Craig L. Bauman Conbstruction (contractor)  0.00
   2    Building Permit  all costs, for any permits obtained by contractor, shall be reimbursed by owners             0.00
   3    Survey          coordinated by contractor, paid for by owners / as needed                                     0.00
   4    Structural Enginee... by architect and owners / provide copy of calcs to contractor                           0.00
   5    HazMat Report   by architect or owners / provide copy of report to contractor if hazordous materials are detected and require removal  0.00
                        prior to demolition
   6    Special Inspections  independent licensed inspection services shall be coordinated by contractor and paid for by owners  0.00
   7    Insurance       general liability policy by contractor / owners to notify their homeowner's insurance carrier they are undergoing  6,700.00
                        construction
                        SITE PREPARATION
   8    Temp Fencing    security fence                                                                              900.00
   9    Temp Storage    by contractor for materials and equipment / 8x10 steel shed in driveway                     965.00
   10   Temp Utilities  all costs associated with providing electricity,natural gas, and water to job site by owners (if city requires a temp  1,150.00
                        power pole allow $700 for permits and $450 to install pole)
   11   Portable Toilet                                                                                           1,100.00
   12   Site Preparation  labor to move in                                                                          400.00
   13   Haz Mat Removal  per report / ALLOWANCE cost plus 15%
   14   Demo            based on 1 layer of roofing, wall and flooring materials / includes hauling to an authorized recycling landfill / extra  16,000.00
                        layers of material T&M
   15   Debris Box      and or hauling for regular job site safety and cleaning                                   2,800.00
   16   Site Excavation  included in concrete work
   17   Site Drainage   splashblocks included / no work indicated
   18   Tree Protection  as ordered by San Jose building dept. T&M
   19   Cleaning        labor for periodic jobsite cleanup (average of 5 hours per week)                          4,400.00
                        CONCRETE
   20   Foundation      new work                                                                                  14,500.00
   21   Foundation      under house                                                                               5,200.00
   22   Flatwork        garage slab, stoops, landings, porches, sidewalks etc.                                    28,000.00
   23   Demo            saw cut stem walls leave footings, cut and haul out slabs for new construction areas      3,900.00
   24   Concrete Repairw... driveway to be covered with 3/4" cdx ply / repairs and tie-in T&M                       800.00
                        CARPENTRY
   25   Rough Carpentry                                                                                           71,000.00
   26   Rough Lumber    includes exterior siding and trim                                                         50,000.00
   27   Rough Hardware                                                                                            10,300.00
   28   Finish Carpentry  interior trim work                                                                      24,000.00
   29   Finish Lumber   ceiling beams                                                                             5,000.00
   30   Finish Carpentry  master closet ALLOWANCE  for job built shelving / 16 hours                              1,200.00
   31   Custom Mouldings  crown,base casing,etc                                                                   8,800.00
   32   Doors           interior and entry                                                                        6,900.00
   33   Door Hardware   ALLOWANCE  for Emtek quality                                                              2,300.00
   34   Finish Hardware  provided by owners and installed by contractor (cabinet knobs, towel bars, TP holders, etc.)
   35   Fencing         remove and re-attach one section of fence for back yard access                              300.00
   36   Siding          front arbor, posts,corbels and siding                                                     9,600.00
   37   Garage Door     double wide wood insulated panel doors similar to photo on plans with openers, 2 remotes and wireless key entry  4,200.00
   38   Windows         includes door from garage to side yard                                                    36,400.00
   39   Skylight         3 total                                                                                  1,200.00
   40   Roofing         composition roofing mat'l 40 yr                                                           21,000.00
   41   Roofing         gutters, downspouts, sheet metal flashings                                                3,200.00
   42   Stucco          patching and new work                                                                     11,250.00
                        MECHANICAL

                                                                              Total