# item Description Total
GENERAL CONDITIONS
1 Plans/Architect by owners / provide 3 hardcopies and pdf files to Craig L. Bauman Conbstruction (contractor) 0.00
2 Building Permit all costs, for any permits obtained by contractor, shall be reimbursed by owners 0.00
3 Survey coordinated by contractor, paid for by owners / as needed 0.00
4 Structural Enginee... by architect and owners / provide copy of calcs to contractor 0.00
5 HazMat Report by architect or owners / provide copy of report to contractor if hazordous materials are detected and require removal 0.00
prior to demolition
6 Special Inspections independent licensed inspection services shall be coordinated by contractor and paid for by owners 0.00
7 Insurance general liability policy by contractor / owners to notify their homeowner's insurance carrier they are undergoing 6,700.00
construction
SITE PREPARATION
8 Temp Fencing security fence 900.00
9 Temp Storage by contractor for materials and equipment / 8x10 steel shed in driveway 965.00
10 Temp Utilities all costs associated with providing electricity,natural gas, and water to job site by owners (if city requires a temp 1,150.00
power pole allow $700 for permits and $450 to install pole)
11 Portable Toilet 1,100.00
12 Site Preparation labor to move in 400.00
13 Haz Mat Removal per report / ALLOWANCE cost plus 15%
14 Demo based on 1 layer of roofing, wall and flooring materials / includes hauling to an authorized recycling landfill / extra 16,000.00
layers of material T&M
15 Debris Box and or hauling for regular job site safety and cleaning 2,800.00
16 Site Excavation included in concrete work
17 Site Drainage splashblocks included / no work indicated
18 Tree Protection as ordered by San Jose building dept. T&M
19 Cleaning labor for periodic jobsite cleanup (average of 5 hours per week) 4,400.00
CONCRETE
20 Foundation new work 14,500.00
21 Foundation under house 5,200.00
22 Flatwork garage slab, stoops, landings, porches, sidewalks etc. 28,000.00
23 Demo saw cut stem walls leave footings, cut and haul out slabs for new construction areas 3,900.00
24 Concrete Repairw... driveway to be covered with 3/4" cdx ply / repairs and tie-in T&M 800.00
CARPENTRY
25 Rough Carpentry 71,000.00
26 Rough Lumber includes exterior siding and trim 50,000.00
27 Rough Hardware 10,300.00
28 Finish Carpentry interior trim work 24,000.00
29 Finish Lumber ceiling beams 5,000.00
30 Finish Carpentry master closet ALLOWANCE for job built shelving / 16 hours 1,200.00
31 Custom Mouldings crown,base casing,etc 8,800.00
32 Doors interior and entry 6,900.00
33 Door Hardware ALLOWANCE for Emtek quality 2,300.00
34 Finish Hardware provided by owners and installed by contractor (cabinet knobs, towel bars, TP holders, etc.)
35 Fencing remove and re-attach one section of fence for back yard access 300.00
36 Siding front arbor, posts,corbels and siding 9,600.00
37 Garage Door double wide wood insulated panel doors similar to photo on plans with openers, 2 remotes and wireless key entry 4,200.00
38 Windows includes door from garage to side yard 36,400.00
39 Skylight 3 total 1,200.00
40 Roofing composition roofing mat'l 40 yr 21,000.00
41 Roofing gutters, downspouts, sheet metal flashings 3,200.00
42 Stucco patching and new work 11,250.00
MECHANICAL
Total