Page 52 - 143 Macquarie Street Main
P. 52
TENDER PROGRAM OVERVIEW OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 2019 2019 2019 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 Target Date for Signing Contract Detailed Design Development Tender Documentation Tender/ Appointment of Head Contractor Authority Approval Procurement of Long Lead Terms On Site Works Practical Completion Preparation of Handover to Property Management Handover to Property Management Handover to Tenants 30th October 30th October - 21st January 22nd January - 17th March 18th March - 28th April 3rd February - 18th June 3rd February - 22nd May 25th May - 26th November 26th November 26th November 26th November 24th December Refer to the Annexure for a full details program. We also welcome the opportunity to discuss our program and milestones further with MEAG to ascertain the best way forward to ensure we deliver in line with the project requirements. 52