Page 160 - CAPE Green Engineering Syllabus 2016.docx_Neat
P. 160
-13- 02265020/CAPE/KMS 2015 SPEC
GREEN ENGINEERING
UNIT 2 - PAPER 02
KEY AND MARK SCHEME
Question 6.
S.O Suggested Response Mark Marks
Allocation KC AK PA
(a) 6 6
Land elevation
Fuel supply
Water supply
Road and rail access
Height of the structure
Disposal of the waste products
Proximity to populated areas
Environmental implications
(1 mark each, any SIX)
(b) 4 4
Maintenance of the equipment which are using
electricity
Redesign to reduce energy costs
Avoid waste – switch off unwanted power
Monitor and control
Power factor correction
(1 mark each, any FOUR)