Page 87 - SAC - DCD - AMB 03 09 20
P. 87
Permit and Service Delivery — Performance Standards + Process Guide City of Encinitas
TI O N 9
Procedure Step Summary
0 Initial Application Submittal E C
S
Within 24 Hours
Enter Project and Tasks into e-Project Source
Within 3 Days
Assign Project to Project Planner
1 Cycle Review #1
Within the First 3 Days
Understand the Project
Make Contact
Route Project for Referral Comments
Make Assignments
Within Remaining Cycle Review Time
Conduct a Field Visit
Evaluate Land Use Compatibility
Conduct Regulatory Review
Evaluate Responses from all Reviewing Departments
Evaluate Citizen Participation Program (CPP)
Prepare the Cycle Review 1 Letter
Review with Supervisor
Release Letter
Update e-Project Source
Contact Applicant
39