Permit and Service Delivery — Performance Standards + Process Guide City of Encinitas
TI O N 9
4 Cycle Review #4
Meet with Applicant
E C
Within the First 3 Days S
Update e-Project Source
Route Project for Referral Comments
Make Assignments
Within Remaining Cycle Review Time
Verify that Issues were Addressed
Evaluate Responses from All Reviewing Departments
Update Supervisor
Prepare the Cycle Review 2 Comment/Incomplete Letter
Review with Supervisor
Release Letter
Contact Applicant
Update e-Project Source
5 Cycle Review CEQA
Make Environmental Determination
Conduct Initial Study
Prepare Draft Environmental Document
Proceed to Public Review
Finalize Environmental Document