Exhibit A-Resolution 2018-37

     The physical date for the addition to the State Trunk Highway System of Segment 1 shall be: December 1,
     2017.

     This Agreement shall be in effect until terminated as determined by the DEPARTMENT. The
     DEPARTMENT shall provide thirty (30) days’ written notice to the VILLAGES prior to terminating this
     Agreement. Unless otherwise required by law, such termination shall not be issued by the DEPARTMENT
     until January 1, 2021. Upon termination, the jurisdiction of Segment 1 shall revert to the jurisdiction of the
     VILLAGES as it existed prior to this Agreement, or as the VILLAGES may otherwise designate by separate
     agreement.

5. Other Considerations

     RIGHT-OF-WAY
     No right-of-way will be conveyed as part of this agreement.

     ACCESS
     No access rights will be conveyed as part of this Agreement. The VILLAGES will continue to issue access
     permits and maintain control over access rights, where owned.

     UTILITIES AND OTHER NON-ACCESS PERMITS
     The VILLAGES will continue to be responsible for all utility coordination and permitting activities within
     highway right-of-way. Leading up to and during construction of the Project, the VILLAGES will submit all
     utility permit applications to the DEPARTMENT for prior approval to ensure utility facilities do not conflict
     with the Project design and construction activities.

     ROUTINE HIGHWAY MAINTENANCE RESPONSIBILITIES
     The VILLAGES will continue to be responsible for routine highway maintenance, including without
     limitation, minor roadway maintenance, ditch and clear area maintenance, winter maintenance, and snow
     and ice removal.

     In light of continued routine highway maintenance responsibilities, the DEPARTMENT shall provide the
     VILLAGES lump sum payments in an amount equal to the General Transportation Aids (GTAs) for which
     the VILLAGES would otherwise be eligible under Section 86.30, Wisconsin Statutes. The lump sum
     payment for maintenance will be made on an annual basis after GTAs are determined. The VILLAGES or
     each individually may request in writing that said payment be credited to other amounts owing the
     DEPARTMENT.

     SYSTEM ROUTING AND NAMING CONVENTIONS
     Highways segments will not be redesignated or renamed as part of this Agreement.

     REHABILITATION/RECONSTRUCTION TREATMENTS
     All roadways and structures will be transferred “as-is” from the VILLAGES to the DEPARTMENT and upon
     termination of this Agreement, all roadways and structures will be transferred “as-is” from the
     DEPARTMENT to the VILLAGES.

     Signatures appear on the following page. The remainder of this page has intentionally been left blank.

Jurisdictional Transfer Agreement                    Page 2 of 3
WisDOT – V. Mt Pleasant, V. Sturtevant (Braun Road)
   141   142   143   144   145   146   147   148   149   150   151