ASSEMBLY SYSTEM TEMPORARY ACCESS PLATFORM INTO THE SHAFT
USER MANUAL V01 SEPTEMBER 2019
4. In a vertical position, release the secondary pins of the hinges “1”,
slightly unfold the platform and lay the platform aside.
5. Disassemble both trays by putting the moths back into position.
6. Take depth measurements of the shaft, and ensure the ideal state of the
floor slab in front of doors where the base of the platform will rest.
Unfold the platform on the landing adjusting to hollow depth
measurements + 200 mm. In this way, after supporting the PAT on the
bottom wall, it will finally have a positive inclination on the horizontal.
Height adjustment through the stairs. Be sure to reinstall the stock with
its corresponding handle.
Horizontal adjustment “3” of the platforms and “4” of the support shoes
on the bottom wall.
18
Rev 01 02/05/2019