       Completion nears at remaining





       phases of South Pars






       Tehran is nearing completion of the 24-phase upstream development of South

       Pars, with work on the last of its 14 onshore refineries not far behind



        IRAN             WORK is nearing completion on the remain-  Zanganeh in September to have reached 700
                         ing development phases of Iran’s South Pars gas  mcm per day, up from 280 mcm per day in 2013.
       WHAT:             field, according to the company responsible for  The minister noted that during this period, 26
       Iran has completed all   the project.                  offshore platforms, 228 wells, 2,160 km of sea
       but one of its 24-phase   Last week, Mohammad Meshkinfam, man-  pipelines and 30 refining trains had been com-
       South Pars development   aging director of Pars Oil and Gas Co. (POGC),  missioned at the field. Meanwhile, over the
       project, with work   told local media outlet IRIB that by the end of  weekend, the oil minister said that the country’s
       ongoing to achieve full   the current Iranian calendar year, which ends  total daily production had reached a record level
       production from the   on March 20, “the development … will be nearly  of 1.04bn cubic metres per day.
       much-discussed phase   completed and we will not have any work left   Production from South Pars began at phases
       11.               except for phase 11 in the offshore sector and the  2 and 3 in 2002, with nine phases entering
                         refinery of phase 14 in the onshore sector, which  production during the presidency of Hassan
       WHY:              will be operational early next year.”  Rouhani.
       South Pars is the   South Pars is split into 24 offshore develop-  Future output levels will be dictated by the
       country’s most important   ment phases and 14 onshore gas refineries which  extent to which Iran is able to counter pressure
       strategic project and   process the gas produced offshore. POGC, a sub-  decline, and there are plans to install 20 heavy
       President Hassan   sidiary of the National Iranian Oil Co. (NIOC),  compression platforms to maintain production
       Rouhani has overseen   holds ultimate responsibility for the projects,  levels at a cost of around $1bn each.
       nine phases entering   with fellow NIOC subsidiary Petropars carrying   Work is ongoing at the remaining phase 11,
       production.       out jobs on the surface and subsurface.  which has been perhaps the highest profile of all
                           The country is home to around 34 trillion  Iranian oil and gas projects following the signing
       WHAT NEXT:        cubic metres of proven natural gas reserves, with  of an integrated petroleum contract (IPC) with
       Questions over the   the supergiant South Pars accounting for around  French super-major Total and China National
       future of production   14 tcm as well as 18bn barrels of gas condensates.  Petroleum Corp. (CNPC) in 2017 targeting pro-
       remain, with Iran   The Islamic Republic holds a 3,700-square  duction to 20.8 bcm per year.
       facing a significant bill   km portion of the 9,700-square km deposit that   The Chinese firm became the lead investor
       to implement efforts   is shared with Qatar, where it is known as the  in SP11 after Total withdrew in August 2018
       to maintain reservoir   North Dome field. Around 80% of the field’s ini-  citing the threat of it incurring US sanctions
       pressure to avoid major   tial gas reserves are believed to remain in place.  should it go ahead with plans. The French firm
       decline.            A week earlier, Meshkinfam denied reports of  had planned to invest an initial $1bn, focusing
                         a pressure drop across the field, noting that since  on a section of the field near the South Pars Oil
                         March 2020, output had increased by 65mn  Layer, adjacent to areas of the field under Qatar’s
                         cubic metres per day of gas following the com-  control.
                         pletion of the phase 16 gas pipeline. “The drop   The company’s 50.1% stake was handed over
                         in gas pressure in South Pars has not occurred to  to CNPC, giving it 80.1%, with Petropars retain-
                         date and forecasts indicate that in the next three  ing the remaining 19.9%.
                         or four years, the drop in gas pressure will begin   Petropars was left as the only remaining part-
                         gradually,” he said.                 ner in the $4.879bn project when CNPC pulled
                           Production from the 23 operational off-  out in 2019.
                         shore phases was reported by Oil Minister Bijan   The Iranian firm kicked off drilling work in