Page 15 - DMEA Week 32
P. 15

DMEA                                           REFINING                                               DMEA








































       Further delays likely at Ugandan




       refining project





        UGANDA           UGANDA’S plan for building a refinery to pro-  that the project might reach the FID stage
                         cess crude oil from fields near Lake Albert is  before the end of this year. Doing so would
       The project will hinge   likely to face further delays.  allow the fields to reach first oil in 2024,
       on progress at oilfield   The East African country has said it wants  with construction work on the refinery com-
       developments.     to construct a plant capable of handling 60,000  mencing in the same year.
                         barrels per day (bpd) of domestically produced   But as Africa Oil + Gas Report noted last
                         crude. Since it is not yet a commercial producer  week, the French company is not now expected
                         of oil, though, this project will hinge on the suc-  to take the FID until 2021 at the earliest. If so, the
                         cessful start of upstream development work at  target date for first oil will have to be pushed back
                         oilfields originally assigned to Tullow Oil (UK/  until at least 2025, and work on the refinery will
                         Ireland). And that project has fallen far behind  have to be postponed as well.
                         schedule.                              Under its agreement with Tullow, Total has
                           Tullow failed to make much progress in  increased its stake in Blocks 1, 1A, 2 and 3A from
                         Uganda last year, largely owing to tax disputes  33.33% to 66.67%. Tullow had been serving as
                         with the government that derailed its farm-  operator of Block 2, while Total was already
                         out agreement with Total (France) and China  operating Blocks 1 and 1A, and CNOOC was
                         National Offshore Oil Corp. (CNOOC). As a  operating Block 3A. Development of these four
                         result, it missed the deadline for making a final  blocks, which contain the Kingfisher and Tilenga
                         investment decision (FID) on its upstream pro-  oilfields, is likely to require about $6.7bn worth
                         ject, which will eventually yield 230,000 bpd.  of investments.
                         This, in turn, pushed back the target date for   Total has also acquired Tullow’s 33.3% stake
                         starting work on the refinery.       in the East Africa Crude Oil Pipeline (EACOP)
                           Since then,  the  parties have  removed  project, which will be used to export most of the
                         some of the obstacles in their path. Tullow  crude extracted from the Ugandan fields. The
                         and Total unveiled a new deal in April, and  French company will work with Uganda and
                         CNOOC has decided not to block the latter  Tanzania to build the $3.55bn pipeline along a
                         company from acquiring 100% of the for-  1,445-km route from Hoima, a city near Lake
                         mer’s Ugandan assets. Ugandan authorities  Albert, to Tanga, a port on the shore of the
                         have signalled their approval of the $575mn  Indian Ocean. When finished, the link will be
                         agreement and have also expressed the hope  able to handle 216,000 bpd. ™



       Week 32   13•August•2020                 www. NEWSBASE .com                                             P15
   10   11   12   13   14   15   16   17   18   19   20