Page 23 - Barr&Barr_Cost Proposal
P. 23
DETAILED GENERAL CONDITIONS
(List all other general conditions expenses as applicable.)
Description Quantity Unit Unit Price Total
On Site Staff (breakdown must be provided for all on-site staff)
Senior Project Manager 23 months $6,411 $147,453
Project Manager 23 months $22,159 $509,657
Reimbursables months $0
Superintendent 20 months $20,676 $413,520
Superintendent 20 months $18,239 $364,780
Reimbursables months $0
Mechanical/Electrical Coordinator 20 months $5,183 $103,660
Mechanical/Electrical Coordinator 19 months $14,009 $266,171
Reimbursables months $0
Project Scheduler 23 months $3,000 $69,000
Reimbursables months $0
Health & Safety Officer 22 months $3,813 $83,886
Reimbursables months $0
Cost Engineer 22 months $3,863 $84,986
Reimbursables months $0
Document Manager 22 months $3,949 $86,878
Reimbursables months $0
Project Accoutant 22 months $4,448 $97,856
Reimbursables months $0
BIM/Logistics Construction 12 months $3,761 $45,132
Coordinator
Reimbursables months $0
Assistant Superintendent 20 months $9,528 $190,560
Assistant Superintendent 20 months $9,658 $193,160
Reimbursables months $0
Field Office Expenses
Extra Plan Copies sets Included
Office Supplies 1 lump sum $207,000 $207,000
Telephone, Data month Included
Office Trailers 23 month $1,400 $32,200
Addendum No. 3 COST PROPOSAL FORM BF-21