Page 23 - Barr&Barr_Cost Proposal
P. 23

DETAILED GENERAL CONDITIONS

                                      (List all other general conditions expenses as applicable.)
                             Description                Quantity           Unit        Unit Price       Total

              On Site Staff (breakdown must be provided for all on-site staff)

                  Senior Project Manager                23           months          $6,411        $147,453

                  Project Manager                       23           months          $22,159       $509,657

                                       Reimbursables                 months                        $0
                  Superintendent                        20           months          $20,676       $413,520

                  Superintendent                        20           months          $18,239       $364,780

                                       Reimbursables                 months                        $0
                  Mechanical/Electrical Coordinator     20           months          $5,183        $103,660

                  Mechanical/Electrical Coordinator     19           months          $14,009       $266,171

                                       Reimbursables                 months                        $0
                  Project Scheduler                     23           months          $3,000        $69,000

                                       Reimbursables                 months                        $0
                  Health & Safety Officer               22           months          $3,813        $83,886

                                       Reimbursables                 months                        $0
                  Cost Engineer                         22           months          $3,863        $84,986


                                       Reimbursables                 months                        $0
                  Document Manager                      22           months          $3,949        $86,878

                                       Reimbursables                 months                        $0
                  Project Accoutant                     22           months          $4,448        $97,856

                                       Reimbursables                 months                        $0
                  BIM/Logistics Construction            12           months          $3,761        $45,132
                  Coordinator
                                       Reimbursables                 months                        $0
                  Assistant Superintendent              20           months          $9,528        $190,560

                  Assistant Superintendent              20           months          $9,658        $193,160

                                       Reimbursables                 months                        $0
              Field Office Expenses
                  Extra Plan Copies                                  sets                          Included


                  Office Supplies                       1            lump sum        $207,000      $207,000
                  Telephone, Data                                    month                         Included

                  Office Trailers                       23           month           $1,400        $32,200



                   Addendum No. 3                  COST PROPOSAL FORM                               BF-21
   18   19   20   21   22   23   24   25   26   27   28