Page 24 - Barr&Barr_Cost Proposal
P. 24
Trailer Utilities 0 month $0 Incl w/ Ele
Trailer Furniture & Equipment lump sum Included
Professional Expenses
Storm Water Plan lump sum Incl w/
Sitework
Licensed Surveyor 1 lump sum $25,000 $25,000
Professional Photogragher 1 lump sum $11,500 $11,500
Temporary Utilities
Temporary Electric lump sum Incl w/ Ele
Temporary Water and Sewer lump sum Incl w/ PLb
Temporary Heating Equipment lump sum Incl w/ HVAC
Fuel for Temporary Heating lump sum Incl w/ HVAC
Construction Site
Fire / Safety lump sum Incl w/ Trades
Winter Protection lump sum Incl w/ Trades
General Hoisting lump sum Incl w/ Trades
Portable Restrooms 23 month $1,000 $23,000
Trash Removal - Labor & Carting 1 lump sum $939,455 $939,455
Protect Trees to Remain lump sum Incl w/
Sitework
Pump Water lump sum Incl w/
Sitework
Snow Removal lump sum Incl w/
Sitework
Storage Trailer 12 month $300 $3,600
Temporary Fencing - Per RFI 14 linear foot $0
Excluded
Wash Glass 1 lump sum $20,125 $20,125
Protect Floors 1 lump sum $15,000 $15,000
Final Cleaning 1 lump sum $50,000 $50,000
Maintain Traffic / Street Clean lump sum Incl w/
Sitework
Trucking lump sum Incl w/ Trades
TOTAL $3,983,579
Addendum No. 3 COST PROPOSAL FORM BF-22