3. FEES AND PROJECT COSTS










































           FEES AND PROJECT COSTS

                                                                                             Everything
           1. Preconstruction Fee
           a.  Barr & Barr would propose a Preconstruction Fee of $12,500, based upon the   Barr & Barr does
             project requirements listed within the RFP. Barr & Barr would look to produce
             as many preconstruction estimates, value management analysis, logistics options   and presents will be
             and schedules to achieve Mercy College goals. We understand the importance
             of communicating the construction activities requirements and the best way to   “Open Book.”
             accomplish this is through our deliverables. Th  ere should never be a limited amount
             or set amount of deliverables your CM is to provide. Th  is is part of our service and
             profession.

           b.   Please reference Section 3A: Preconstruction Services/Section 3B: Construction
              Services for our detailed “Scope of Services” and Section 4: Proposed Project
              Staff  for the individuals who are providing these services.

           c.   Please reference Section 4: Proposed Project Staff   for our Preconstruction and
             Construction Organizational Charts. See Section 3C: Cost Breakdown for our
             cost breakdown.

           d.    Th  e Preconstruction fee listed will be separate from and additional to the
              Construction Phase fee.

           e.  Limitations (not included) to the Preconstruction Lump Sum Fee includes:

           •   International travel or travel requiring air fl ights
           •   Mock-ups
           •   Permitting/approval process
           •   Controlled  Inspections
           •   Testing
           •   Exploratory Investigations