Page 66 - Barr&Barr_Technical Proposal
P. 66
Cornell - VEEC Project 50% CD Schedule 2019 2018 ep August July June May April March February January December November October eptembe August July June May April March February January December November October eptembe 3rd Floor 4th Floor 1st Floor 1st Floor Mezz Roof MER Excavation Caissons/Piles Grade Beams & Pile Caps Backfill Frostwalls Backfill Underground Utilities Backfill Mat Slab on Grade Structural Steel Anchor Bolt Survey Structrual Steel Crane
July August CONSTRUCTION Mobilization Site Preparation
June
May
April
Summary
March
February
2017 January Milestone
December
November
October
eptembe Progress
August
Fri 4/20/18 Fri 5/18/18 Fri 6/15/18 Fri 5/18/18 Fri 7/13/18 Thu 7/18/19 Fri 9/8/17 Fri 9/22/17 Fri 10/6/17 Fri 11/24/17 Fri 12/22/17 Fri 12/29/17 Fri 1/19/18 Fri 1/26/18 Fri 1/26/18 Fri 1/26/18 Wed 4/4/18 Fri 1/5/18 Wed 1/31/18 Wed 3/21/18 Wed 3/28/18 Wed 4/11/18 Wed 6/6/18 Wed 6/27/18 Wed 8/1/18 Thu 4/18/19 Tue 7/10/18 Tue 8/21/18 Tue 8/28/18 Tue 9/25/18 Tue 10/16/18 Tue 10/23/18 Thu 10/25/18 Tue 1/1/19 Wed 6/6/18 Wed 6/13/18 Wed 6/27/
Finish Wed 10/24/18 Wed 10/24/18 Wed 10/31/18 Wed 10/24/18 Wed 10/24/18 Wed 10/31/18 Wed 12/26/18
Task
Mon 3/26/18 Mon 4/23/18 Mon 5/21/18 Mon 4/23/18 Mon 6/18/18 Mon 9/4/17 Mon 9/4/17 Mon 9/11/17 Mon 9/25/17 Mon 10/9/17 Mon 11/13/17 Mon 12/25/17 Mon 12/25/17 Mon 1/22/18 Mon 1/1/18 Mon 1/22/18 Thu 3/15/18 Mon 1/1/18 Mon 1/29/18 Thu 2/1/18 Thu 2/15/18 Thu 3/8/18 Thu 3/29/18 Thu 6/7/18 Thu 6/7/18 Fri 4/5/19 Wed 6/6/18 Wed 7/4/18 Wed 8/1/18 Wed 8/29/18 Wed 9/12/18 Wed 9/26/18 Wed 9/26/18 Wed 9/26/18 Thu 10/25/18 Wed 10/10/18 Wed 6/6/18 Thu
Start
Duration 20 days 20 days 20 days 20 days 20 days 489 days? 5 days 10 days 10 days 35 days 30 days 5 days 20 days 5 days 20 days 5 days 15 days 5 days 3 days 35 days 30 days 25 days 50 days 15 days 40 days 10 days 25 days 35 days 20 days 20 days 31 days 21 days 15 days 20 days 1 day? 60 days 0 days 5 days 10 days 25 days 10 days 28 days 5 days 20 days 20 days 20 days 10 days 15 days 10 days 10 days 7 days 10 days 10 days
BARR & BARR Task Name ID 3rd Floor 195 4th Floor 196 1st Floor 197 1st Floor Mezz 198 Roof MER 199 200 201 CONSTRUCTION Mobilization 202 Site Preparation 203 Excavation 204 Caissons/Piles 205 Grade Beams & Pile Caps 206 Backfill 207 Frostwalls 208 Backfill 209 Underground Utilities 210 Backfill 211 Mat Slab on Grade 212 Structural Steel Anchor Bolt Survey 213 Structrual Steel Crane Mobilization 214 Structural Steel Erection 215 Str Stl Metal