List of Projects Implemented in 2012
No. Project Description Contractor Contract Sum
37 The Proposed Site Investigation Survey, Design, Supply, Delivery, Kemena Holding Sdn Bhd 2,997,600.00
Construction, Completion, Including testing and commissioning of a now
storage tank at Long Lama treatment plant, Miri Division Sarawak.
PWD/HO/B055/2012 KKLW/BALB/4/2012
38 Design and build contract the proposed improvement work for Sungai Asap, PPES Works (Sarawak) Sdn Bhd 3,799,000.00
Water Supply System, Bakun, Kapit Division, Sarawak PWD/HO/B094/2012
39 Cadangan Pembinaan dan penyiapan 1 block gelanggang skuasy di SK Puncak Diniar Sdn Bhd 1,624,445.9
Jalan Bintang, Bahagian Miri, Sarawak. PWD/HO/B108/2012