Page 30 - Achievement Report 2012-2016 Northern Regional Office eBook
P. 30

Pre-Construction                       Construction                           Post-Construction
                                                     1 st  valuation   Subsequent
                                                      (Cls 28.1)     valuation
          Letter of          Site Possession         Interim Cert    (Cls 28.1)            Defect Liability Period
          Acceptance           (Cls 38.1)             (Cls 28.3)                                                  Final Certificate
                                                     POH 30 days
                                                      (Cls 28.6)    Next Interim     Handover                       (Cls 31.3)
                                                                      Cert
                                                                     (Cls 28.3)                     CMGD
                 Pre-Construction   Commencement                    POH 30 days    Date Completion  (Cls 48.4)
                   Meeting           of Work                                         (Cls 39.1)
                                                                                                              3 month
                                                                                                 Complete?
             Contractor to     Date Commence (Cls 38.2)     Require            If any?        Certificate   DLP Commence  Final Certificate
             submit                                                         Dispute?          Practical   (Cls 48.1)  > State final balance due from
                                                                                                      Contractor
                                                                                              Completion
                                                                                                                    the Govt. to the Contractor  or
             > Work program    Contractor to submit:   SO Instruction (Cls  5 . 1a-i)  Arbitration  (Cls 39.6)  submit Final      vice versa (Cls 31.4)
                                                                            (Cls 66) (only
                within 14 days for   > Performance                          commence after            Account    > Statutory Declaration (Cls 31.5)
                                                                                                      (Cls 31.1)
                SO approval       Bond/Performance       Variation (Cls 24.1)  CPC)            Ref: JKR 203S – Pind.3/2008
                (Cls 12.1)        Guarantee Sum (Cls 13)  Ref: JKR-APK (Pind 3/2008)  Breach?                    > Final Payment (Ref : JKR 66A
                               > Insurance (Cls 15 & 18)                    > Default by        Not Complete?       (Pind. 2/1999)
                                                       Expand PC/Provisional Sum   Contractor    Certificate Non
                                                                               (Cls 51)
             Delay In Giving   If Govt Delay, give site     (Cls 34)        > Default by Govt.   Completion  LAD (Cls 40.2)
                                                                                              (Cls 40.1)
             Possession Of Site   possession within 90 days,                   (Cls 55)       Ref: JKR 203X – Pind.2/2008
             (Cls 38.4)        within 14 days:             Apply EOT        Compulsory
                                                                            Termination?
             > Refer to JKR    > Proceed without L&E or   Ref: JKR-JKLM  (Pind 1/2008)  > National Interest
                guideline         terminate (Cls 38.6)                         (Cls 52)        Extended Time?
                                                         Notice L&E (Cls 44.1)  > Corruption (Cls 53)  Certificate of   New Completion
                                                                            Mutual Termination   Delay & EOT   Date
                                                                            (Cls 50.3)        (Cls 43.1)
                                        Site Possession                                       Ref: JKR 203T – Pind.5/2008
                                         (Cls 38.3)
                                                            Sectional Completion                    Partial Possession?
                                                       Sectional Completion (Cls 41.1)
                                                       Separate
                                                                                        Certificate Partial Completion   DLP   CMGD
                                                       a)  CPC                          (Cls 42.1)      Commence  (Cls 42.1c)
                                                       b)  Delay & EOT                  Ref: JKR 203W – Pind.1/2008  (Cls 42.1b)
                                                       c)  LAD
                                                       d)  DLP
      26        Achievement Report 2012 - 2016
                Northern Regional Office  Jabatan Kerja Raya Sarawak