Page 30 - Achievement Report 2012-2016 Northern Regional Office eBook
P. 30
Pre-Construction Construction Post-Construction
1 st valuation Subsequent
(Cls 28.1) valuation
Letter of Site Possession Interim Cert (Cls 28.1) Defect Liability Period
Acceptance (Cls 38.1) (Cls 28.3) Final Certificate
POH 30 days
(Cls 28.6) Next Interim Handover (Cls 31.3)
Cert
(Cls 28.3) CMGD
Pre-Construction Commencement POH 30 days Date Completion (Cls 48.4)
Meeting of Work (Cls 39.1)
3 month
Complete?
Contractor to Date Commence (Cls 38.2) Require If any? Certificate DLP Commence Final Certificate
submit Dispute? Practical (Cls 48.1) > State final balance due from
Contractor
Completion
the Govt. to the Contractor or
> Work program Contractor to submit: SO Instruction (Cls 5 . 1a-i) Arbitration (Cls 39.6) submit Final vice versa (Cls 31.4)
(Cls 66) (only
within 14 days for > Performance commence after Account > Statutory Declaration (Cls 31.5)
(Cls 31.1)
SO approval Bond/Performance Variation (Cls 24.1) CPC) Ref: JKR 203S – Pind.3/2008
(Cls 12.1) Guarantee Sum (Cls 13) Ref: JKR-APK (Pind 3/2008) Breach? > Final Payment (Ref : JKR 66A
> Insurance (Cls 15 & 18) > Default by Not Complete? (Pind. 2/1999)
Expand PC/Provisional Sum Contractor Certificate Non
(Cls 51)
Delay In Giving If Govt Delay, give site (Cls 34) > Default by Govt. Completion LAD (Cls 40.2)
(Cls 40.1)
Possession Of Site possession within 90 days, (Cls 55) Ref: JKR 203X – Pind.2/2008
(Cls 38.4) within 14 days: Apply EOT Compulsory
Termination?
> Refer to JKR > Proceed without L&E or Ref: JKR-JKLM (Pind 1/2008) > National Interest
guideline terminate (Cls 38.6) (Cls 52) Extended Time?
Notice L&E (Cls 44.1) > Corruption (Cls 53) Certificate of New Completion
Mutual Termination Delay & EOT Date
(Cls 50.3) (Cls 43.1)
Site Possession Ref: JKR 203T – Pind.5/2008
(Cls 38.3)
Sectional Completion Partial Possession?
Sectional Completion (Cls 41.1)
Separate
Certificate Partial Completion DLP CMGD
a) CPC (Cls 42.1) Commence (Cls 42.1c)
b) Delay & EOT Ref: JKR 203W – Pind.1/2008 (Cls 42.1b)
c) LAD
d) DLP
26 Achievement Report 2012 - 2016
Northern Regional Office Jabatan Kerja Raya Sarawak