Page 60 - KOP Panborneo Highway Report Card Jan-june 2017
P. 60
Quality assurance & control Pile Tests
Bored pile & 250x250 RC PILE
Type of Test Scheduled Total
Item Description of Works Done & Pass
Required Nos. of Tests
1 At Bridge 1A & 1B Static Load Test 2 1
PDA 17 2
Sonic Logging 8 0
PIT 8 0
SPT (N>=300) 76 38
2 At Bridge 2A & 2B Static Load Test 2 2
PDA 17 12
Sonic Logging 8 4
PIT 8 4
SPT (N>=300) 38 33
3 At Bridge 3A & 3B Static Load Test 1 1
PDA 15 4
Sonic Logging 6 3
PIT 6 4
SPT (N>=300) 60 30
4 At Bridge 4A & 4B Static Load Test 1 1
PDA 15 4
Sonic Logging 6 4
PIT 6 4
57 SPT (N>=300) 60 30