Task 5: Economic Analysis
               The CONSULTANT will determine economic benefit to property value, retails sales and resulting and
               resulting potential financial contribution options for transit service.

               An estimate of the potential range of revenues from possible development scenarios and/or value
               capture taxes will be developed for each alternative. A "high" and "low" range shall be determined and
               presented based on assumptions about the amount of new development generated by the project, the
               amount and nature of development that could occur net of potential infrastructure or land
               assembly/preparation costs, and the amount of tax or joint development contributions made by private
               sector participant(s). The timing and probability of the potential revenue stream from development will
               be estimated.

               Schedule:      Concurrent with Task 4
               Deliverables:   Technical Memorandum #3 - Economic Analysis


               Task 6: Final Station Area Plan
               The CONSULTANT will provide a Final Station Area Plan that will incorporate:
                   •  Technical Memorandum #2 - Existing Conditions Summary
                   •  Station Area Plan which consists of technical studies, analysis conducted and comments made
                       during Community Workshops
                   •  Technical Memorandum #3 - Economic Analysis
                   •  Response to comments made during the community workshops and meetings

               Schedule:      Four (4) weeks
               Deliverables:   Draft and Final Station Area Plan/Report





































                                                              3