Page 17 - Property Rights in the Philippine A Time and Cost Study_July 2017
P. 17

Table 1. Timeline for Residential Free Patent Issuance, Sporadic

                             STAGE                NUMBER OF PROCESSING                     NOTES
                                                             DAYS
                 Sporadic Adjudication                        70                10 days for investigation
                                                                                60 days for compliance with
                                                                                requirements
                 Subdivision Survey                           60                Includes applying for survey
                                                                                authority, securing the survey
                                                                                data, actual survey, approval.
                                                                                Assumes that the clients is able
                                                                                to pay for the survey right away.
                 CENRO Processing                             120               Single application processing
                                                                                can be fast (compared to batch
                                                                                processing for Systematic
                                                                                Adjudication) and can be finished
                                                                                in 40 days if application
                                                                                requirements are complete
                 PENRO Processing                              5

                 ROD Registration and Title                   60                Can take up to 2 months
                 Issuance


               Table 2. Timeline for Residential Free Patent Issuance, Systematic
                                                                           15
                             STAGE                NUMBER OF PROCESSING                     NOTES
                                                             DAYS
                 Systematic Adjudication                      320               130 days for preparation of lot
                                                                                information
                                                                                60 days for RLTA
                                                                                10 days for Barangay Assembly
                                                                                60 days for actual adjudication
                                                                                60 days for compliance with
                                                                                requirements
                 Subdivision Survey                           60                Can be longer as there are more
                                                                                lots to be surveyed
                 CENRO Processing                             120               Batch processing

                 PENRO Processing                              5                Mostly re-validation and
                                                                                ministerial

                 ROD Registration and Title                   60                Can be longer
                 Issuance






               15  Systematic Adjudication, Surveying, and CENRO Processing can take longer with Systematic Adjudication because it involves a
               number of applications in a batch.