Activity Because of the perceived cost, distance, complication,
Applicant, with the assistance of complexity of the process, or adverse relations) that lot
DPLI, secures required supporting many applicants opt for occupants tend to abandon
papers and submits to DPLI “Package Deals” which their application
ranges from PhP
2,000.00 to PhP
15,000.00.
PREPARATION OF
COMPLETED STAFF WORK
CARPETA
Actor Completed Staff Work
CENRO Land Inspector • Titling Application
Titling application with Activities • Final Land
7 complete supporting Investigation Report NA 2 days
documents 4. CENRO Land Inspector • Barangay Certification
assesses completeness of • Zoning Clearance
supporting documents
5. Prepare investigation • Supporting documents
report narrating the findings • Photos
during the investigation/
ocular inspection
6. Endorses applications to
the CENRO Land
Management Officer
36