Page 51 - Property Rights in the Philippine A Time and Cost Study_July 2017
P. 51
Table 6. Input-Process-Output Table of Subdivision Survey
INPUT PROCESS OUTPUT COST DURATION
PREPARATION FOR
SURVEY
1 Actor
Geodetic Engineer (GE)
Activities
Actor
GE (Private or Admin)
Activity
1.1 Lot/s to be surveyed Gathers lot information from the 1. Lot number 1 day
2. Survey number
lot owner through face-to-face
meeting, e-mail messages,
phone calls, etc.
Actor
1. Survey number GE (Private or Admin)
2. Survey number Activity 1. True copy of approved
1.2 3. Request form Goes to the DENR Regional survey plan 3 days
(provided by the Office, fills up a Request Form 2. LDC
DENR Regional and request for approved
Office) survey plan and Lot Data
Computation (LDC)
1. True copy of Actor Information on:
approved survey GE (Private or Admin) • Mojons
plan Activity • Claimants
1.3 2. LDC Interviews lot occupants/ • Payment 1 day
claimants/ clients • Documentary requirements
• Etc