Opinion of Probable Cost
                                                                                             Birchwood Design Group
                                                                                                    Jun-16


           Opinion of Probable Cost - Fay Memorial Park


                                  Item                    Quantity  Unit  Unit Price  Total
              Site Preparation/Demolition
                                            Temporary Utilities  1   LS     $8,000   $8,000
                                     Temporary Chainlink Fence  1500  LF     $6      $9,000
                             Remove & Dispose baseball backstop  3,307  SY   $9      $28,200
                                                   Silt Sock  400    LF      $3      $1,200
                                              Inlet Protection  4    EA     $300     $1,200
                                                  Subtotal                           $47,600

              Site Improvements
                                          Fine Grading of Field  1   LS    $10,000   $10,000
                                      Natural Grass field ~ @ 6"
                                                Haul in of topsoil  600  CY  $25     $15,000
                                                     Irrigation  1   LS    $40,000   $40,000
                                               Field Drainage  1     LS    $20,000   $20,000
                                  Stone Dust Path improvements   900  LF     $15     $13,500                                                                                                                                            SECTION 5 -  RECOMMENDATIONS/ PRIORITIZATION
                                                  Subtotal                           $98,500


                  SUBTOTAL OF SITE CONSTRUCTION ITEMS              TOTAL            $146,100
              GENERAL CONDITIONS, BOND, CONTRACTOR OH&P                              $14,610
                              CONTINGENCY                                            $7,305
                                  TOTAL                                             $169,000