Page 136 - Southborough Final Package
P. 136
Opinion of Probable Cost
Birchwood Design Group
Jun-16
Opinion of Probable Cost - Woodward / Choate Athletic Fields
Item Quantity Unit Unit Price Total
Site Preparation/Demolition
Temporary Utilities 1 LS $8,000 $8,000
Temporary Chainlink Fence 2000 LF $6 $12,000
Remove & Dispose Softball Backstop 3,307 SY $9 $28,200
Silt Sock 2,000 LF $3 $6,000
Inlet Protection 4 EA $300 $1,200
Subtotal $55,400
Site Improvements
Fine Grading of Turf Fields 1 LS $25,000 $25,000
Haul in of topsoil 2,518 CY $25 $63,000
Additional Irrigation 1 LS $60,000 $60,000
Field Drainage 1 LS $70,000 $70,000
Seeding 3 Acre $3,000 $9,400
Subtotal $227,400 SECTION 5 - RECOMMENDATIONS/ PRIORITIZATION
SUBTOTAL OF SITE CONSTRUCTION ITEMS TOTAL $282,800
GENERAL CONDITIONS, BOND, CONTRACTOR OH&P $28,280
CONTINGENCY $14,140
TOTAL $326,000
SOUTHBOROUGH ATHLETIC MASTER PLAN
136