Opinion of Probable Cost
                                                                                             Birchwood Design Group
                                                                                                    Jun-16


           Opinion of Probable Cost - Woodward / Choate Athletic Fields

                                 Item                   Quantity  Unit  Unit Price  Total

              Site Preparation/Demolition
                                          Temporary Utilities  1  LS     $8,000     $8,000
                                   Temporary Chainlink Fence  2000  LF    $6       $12,000
                            Remove & Dispose Softball Backstop  3,307  SY  $9      $28,200
                                                Silt Sock  2,000  LF       $3       $6,000
                                            Inlet Protection  4   EA      $300      $1,200
                                                Subtotal                           $55,400

              Site Improvements
                                   Fine Grading of Turf Fields  1  LS    $25,000   $25,000
                                             Haul in of topsoil  2,518  CY  $25    $63,000
                                         Additional Irrigation  1  LS   $60,000    $60,000
                                            Field Drainage  1     LS    $70,000    $70,000
                                                   Seeding  3     Acre   $3,000     $9,400
                                                Subtotal                           $227,400                                                                                                                                             SECTION 5 -  RECOMMENDATIONS/ PRIORITIZATION


                 SUBTOTAL OF SITE CONSTRUCTION ITEMS             TOTAL             $282,800
             GENERAL CONDITIONS, BOND, CONTRACTOR OH&P                             $28,280
                            CONTINGENCY                                            $14,140
                                TOTAL                                             $326,000












































        SOUTHBOROUGH ATHLETIC MASTER PLAN