Page 140 - Southborough Final Package
P. 140
FIELD H:
NATURAL TURF PRACTICE FIELDS
Neary School has a large expanse of open space allowing for multiple programs to occur on site. It has
great parking and is centrally located to town providing great access to the sites amenities. Previous
construction documents show a former full size baseball field on site which has become over grown and
looks to be in transition to a green space.
Recommendations: Neary School has some of the largest public open spaces in the town. The site
can fit multiple varying sized soccer fields, it has tennis courts, volleyball and a softball field. The town
currently lacks the space to have a full size 90’ baseball diamond as originally constructed on this site.
Depending on budget, phasing and future planning/relocation of facilities the town may consider rein-
stalling a full size 90’ baseball diamond to accommodate upper age levels and upper levels of play. The
baseball field size would still allow a full size soccer field in the outfield for practice or even game play.
The current 90’ baseball field at Mary Finn Elementary School is under size and grading in the field is
unsafe for the athletes. The Softball field at Neary School may be able to be relocated depending on SECTION 5 - RECOMMENDATIONS/ PRIORITIZATION
future plans for Mary Finn elementary allowing yet another open space for a smaller soccer field. As
budget allows the town may also consider a larger size synthetic turf surface that could be used for both
a full size baseball field and the accommodation for a full size soccer field in the outfield. The synthetic
turf takes some hassle out of maintenance of a full size baseball infield and the surface also allows for
play after in-climate weather for both baseball and soccer.
High Priority There is not enough known about the use the volleyball court but it looks to be used and well main-
tained. There is also not enough user information on the tennis courts, but they looked to be used on a
1.0 ADA Accessible walk regular basis. There is some significant cracking occurring in the surface and although it is not current-
ly in the playing area the court should be replaced should the cracking spread to the playing surface
2.0 Drainage where it may cause risk of injury to the athlete.
Medium Priority
1.0 Restrooms -NEARY SCHOOL
SOUTHBOROUGH ATHLETIC MASTER PLAN
140