Opinion of Probable Cost
                                                                                       Birchwood Design Group
                                                                                             Jun-16

           Opinion of Probable Cost - Trottier Track and Fields


                             Item                Quantity  Unit  Unit Price  Total
              Site Preparation/Demolition
                                     Temporary Utilities  1  LS  $8,000      $8,000
                              Temporary Chainlink Fence  2500  LF  $6       $15,000
                          Remove & Dispose Existing Track  1  LS  $20,000   $20,000
                                           Silt Sock  1,500  LF   $3         $4,500
                                          Subtotal                          $47,500
              Site Improvements
                         Fine Grading of Synthetic Turf Field  1  LS  $25,000  $25,000
                HMA with 6" Stone base- D Areas and Long Jump  3,588  SY  $32  $114,900
                          Natural Grass field ~ 70000sf @ 6"
                                        Haul in of topsoil  1,296  CY  $25  $32,400
                              Fine Grading Practice Field   1  LS  $15,000  $15,000
                                              Irrigation  1  LS  $40,000    $40,000
                                 Practice Field Drainage  1  LS  $20,000    $20,000
                                              Seeding  2  Acre   $3,000      $6,000
                                       Synthetic Turf  87,516  SF  $4.25    $372,000
                                Football Soccer Goal Pak  1  LS  $35,000    $35,000                                                                                                                                                     SECTION 5 -  RECOMMENDATIONS/ PRIORITIZATION
                                       Track Surface  7,114  SY   $50       $355,700
                         Base and Finishing Stone Subbase  1  LS  $120,000  $120,000
                                 Slot Drain/Trench Drain  1,305  LF  $60    $78,300
                                      PCC Field Curb  440  LF     $25       $11,000
                                       Field Drainage  1   LS    $50,000    $50,000
                                 Discuss Hammer Cage  2    LS    $25,000    $50,000
                                           Shotput  2      EA    $7,500     $15,000
                             Long Jump runways and  Pits  2  EA  $8,000     $16,000
                                      Javelin Runway  1    EA    $8,000      $8,000
                                          Subtotal                         $1,364,300


               SUBTOTAL OF SITE CONSTRUCTION ITEMS       TOTAL             $1,411,800
            GENERAL CONDITIONS, BOND, CONTRACTOR OH&P                       $141,180
                          CONTINGENCY                                       $70,590
                             TOTAL                                        $1,624,000