II. DETAILED ACCOMPLISHMENT REPORT
TIME FRAME ACTIONS TAKEN ACCOMPLISHMENT / REMARKS
OUTPUT
Week 1 • Consulted the TA and Apply revisions and took Completed
(January 27 – TC for the revision of note on the to be developed
31, 2020) the papers and the to functionality of the system
be developed
functionality of the
system
• Finalizing the user The researchers finished Completed
Week 2 interface of the designing the website’s
February 3 – website interface
7, 2020 • Started developing the
main function of the
system
• Test run the design The researcher collected Completed
Week 3 using localhost server data from the test run and
February 10 – to understand the user concluded what change are
14, 2020 experience of the to be applied to the design
website
• Finished developing Main function of the system Completed
Week 4 the main functions of is up and running
February 17 – the system
21, 2020 • Test run the system
using localhost server
for debugging
• Started developing
additional features of
the system
• Test run the system Debugged the system Completed
Week 5 using localhost server
February 24 – for debugging
28, 2020
• Half way done in Adding students and chat Completed
Week 6 developing the feature is up and running
March 2 – 6, additional features of
2020 the system
• Test run the system
using localhost server
to debug the additional
features added
Week 7 • Applied the developed Debugged the additional Completed
March 9 – 13, additional features of features added
2020 the system to the user
interface of the
*Start of ECQ website