11.0 Wheel Loss or Instances of Loose Wheels




        Where there are any reported instances of wheel loss or wheel looseness, Group Companies must ensure
        there is a written policy for investigating, reporting and escalating all such issues in a timely manner.

        Investigations and subsequent reports must include all pertinent information to establish, where possible,
        root cause and include any deviations from this standard and any required remedial action.
        In parallel with the investigation process, additional containment actions such as a wheel security fleet
        check are recommended.

        Where such investigation drives a change to policy, procedure or paperwork, training must be provided to
        update employees and ensure ongoing compliance.


        12.0 People



        The Engineering Director, or equivalent, must:



         Ensure that safety is taken into account at every specific stage of the wheel and tyre fitment process to
            E
        nsure that the tools and equipment required for wheel and tyre fitment vehicles are provided
         Ensure there are robust processes in place to ensure compliance with environmental requirements.

        Engineering Manager (or equivalent) must:

        Ensure that all engineers required to undertake any part of the wheel fitment process are trained and
            competent to do so.
         Ensure that the required number of engineers are trained and competent to fulfil wheel fitment
            requirements safely.
         Audit the wheel fitment process on a regular basis to ensure all aspects of this global standard are met.
          Ensure all tooling and equipment is maintained.
          Ensure all wheels and tyres being used on vehicles are inspected for compliance to specifications and
            absence of defects before first use

        Engineers must not:

        be permitted to undertake any part of the wheel fitment process without being fully trained and
           competent in the specific areas.


        The engineer´s line manager must:

              The engineer´s line Manager will be held accountable for ensuring Engineers have the
               necessary training, experience and currency to meet the legal requirements as well as those in the
               Group Maintenance Standards and policies, and that this documentation is maintained and
               completed. Failure to do so will be dealt with in accordance with the company’s progressive
               discipline policy and serious failings may be considered as gross misconduct.




                                              Global Maintenance Standard: Wheel Fitment & Security            10
   8   9   10   11   12   13   14   15   16   17   18