Timeline for In scope deliverables
Q3 – Q1 FY19
Q2 • Pre Fab Custom capabilities
• Refine Staffing standards
• APT 2.0 programming for Water and Fire
Q1 • Pre Fab Ready- Digital Factory • Remote commissioning capabilities
• Adjust Sales Estimating
• Logistics in place
• Engineering and Submittal Standards
• NIE/NIS Team in place in all Zones
• DSC ready to handle warranty
Impact • ZTC Staffing • Execution Staffing
• Centralize Engineering
(Design, Programming and Graphics)
• Zone Technical Specialist Staffing
• Digital Deployment Package
• APT mandatory
• Remote access to Site
• Pilot of Panel Fab with Digital Factory
• Logistics and Warehouse resources
• Subcontracting Scope Reduction
• Digital Service Center preparedness
• Implementation of ZTC Technology