Page 10 - August_10th_SrSteerCo_e_bookwof
P. 10
Digital Deployment
The digital deployment package is the product of the ZTC
The engineering workflow is designed around building the DDP
What we are Each step adds value to the package.
delivering? It is additive as the DDP makes its way thru the production cycle.
The digital deployment package includes:
Submittals, Programs Graphics, Commissioning Checklists, CrSP, System Licensing information,
Progression Witness Test, DSC setup info., etc.
When we will October 1 , 2017 - Submittals Programs Graphics, Commissioning Checklists, CrSP
deliver it? January 1, 2017 - Panels, Enabled Graphics, DSC warranty support, System Licensing, FDD intro package.
Customer
Who will be Project Execution team
impacted? Digital Service Center
Specialists and technicians
Confidential © Siemens AG 2017
Page 10 08/07/2017 Names are for example only Siemens Industry, Inc.