Future of Project Logistics – Planning Material Deliveries
Standard Delivery Options
Installation Schedule drives material logistics 1. Direct to Job Site (JIT)
Schedule Greatly reduces overall shipping and handling,
requires more logistics planning/coordination.
PM sets
installation Logistics
schedule.
B.O.M. 2. Drop-ship to Subcon
Shipping to subcontractors (installers or
Planning manufacturers) reduces shipping and
handling steps for Siemens.
ENG defines
material PLO plans and
requirements tracks material
and segments orders per Pre-fab
BOM per installation 3. Value-Add Warehouse
installation schedule using Involves more shipping and Warehouse
schedule. available
logistics data handling, but allows Siemens to
and concepts. perform various value adding steps
(kitting, pre-fab, testing, etc.)
Confidential© Siemens AG 2017 PLO = Project Logistics Operation (a new position)