Page 22 - Rail Express - September 2019
P. 22

OPERATIONS




           The all-seeing NOC








               PhilMarsh visits Network Rail’s National Operations Centre, which monitors

               the entirenetwork around the clock to keep passenger and freight services
                                              running as smoothlyaspossible.


               HE statistics of around 25,000     mechanics of the situation. The very     Eastleigh –which has aTOPSreporting
               trains aday operating across       proactivepartnership between the         facility –togotoanengineering
         T20,000 miles of Network Rail track      Samaritans charity and the rail industry  worksite that does not.
          every 24 hours arewell rehearsed, and   wasvery much in evidence in this             When engineering work hasbeen
          the National Operations Centrecould     sad process.                             completed, the empty wagons maynot
          be described as the heart of these          One area left to the police to       return to Eastleigh, but theywillbein
          operations. From its base in Milton     manageisthe growing problem of           the system as being thereand not at
          Keynes, the NOC monitors all train      ‘Person in precarious position’ incidents,  the worksite,which is thereforesuitably
          movements on a24/7 basis, split into    wheresomebody is posing athreat to       corrected by the relocation facility.This
          apassengerteam and the Freight and      themselves. Thereweretwo incidents       function is also used when alocomotive
          National Passenger Operators (FNPO)     on July15–one near Potters Bar at        is movedbyroad and is ‘virtually
          organisation.                           03.45 and one at Abercynon at 21.15      relocated’ when it reappearsonthe
             To getafeelfor NOC operations,       that collectivelycaused around 1300      network, and the NOC team sends afax
          Ijoined the passenger team’s duty       minutes' delay.                          confirmation to those involved foran
          controller David WiltshireonJune28and       Following the incident at Lewisham   audit trail.
          the FNPO’s freight service delivery                                                        TOPS also sendsvarious
          managers (FSDMs) John Phillips   “The team is sadlywell-rehearsed                       alerts to theNOC team, such
          and Steve Dexter on July 15.             in liaising with coroners,                     as seeminglyoverweightor
             By 07.00, when Ijoined David                                                         unregistered vehicles, usually
          Wiltshire, he had already spoken         undertakers and police”                        caused by inputting errors. David
          to every route controller to gain                                                       Wiltshire, demonstrating his
          an overviewofthe network                                                                expertise gained overa47-year
          situation inherited from the night shift,  in March2018, when passengers on a    railway career,said: “The net cargo
          andwas monitoring every situation       stranded train opted to open the doors   weight can be confused with the gross
          that had the potential to escalate into  and climb down onto the trackswhile     wagonweight, which might have been
          serious disruption.                     the third-railwas stilllive, apolicyof   erroneouslyinput into the system,
             The NOC receives around              assessing the risk to passengers on      which in turn automaticallyassumes
          100 emails every hour from route        trapped trains wasintroduced. Trains     incorrect loading and breaching of the
          controllers, advising on incidents      arenow held in platforms wherever        axle weight limits.”
          ranging from the ridiculous and the     possible to avoid emergencyor                Occasionally, spoiltrains are
          downright tragic, but the policyisnot   unplanned evacuations.                   incorrectlyloaded by filling onlyone
          to intervene unless thereispotential to                                          side of awagon. This increases the
          affect overall network performance.     GOING WILD                               axle loading on that side and creates
             On July15at11.02, forexample, a      The NOC is aone-stop shop forall         the potential foraderailment, which
          sombrero-wearing drunk wasreported      route controllers, and uses 34 screens   triggers aWILD alarm. Wetspoilalso
          on the track in the Sheffield area, while  to monitor everythingthatmoves (or    does the same, as it weighs morethan
          the tragic suicide of ateenager five     does not move)using livefeeds from       the dry variety.
          hours later brought avery downbeat      the TRUSTand TOPS computers, plus            On June 28, aWILD activation was
          mood to the office.                     safety critical systems like Wheel       registered at 06.58 when the 06.12
             Twosuicides occurred on both days    Impact Load Detectors (WILD) and Hot     Liverpool Street to Braintree service
          Iwas in the NOC, and the team is sadly  AxleboxDetectors.                        (operated by EMUs Nos. 321329+
          well-rehearsed in liaising with coroners,   The NOC has high-levelTOPS           321433) activated the Ingatestone
          undertakers, police and the statutory   permissions–suchasthe relocation         Down Main line WILD with awheelflat         ¬ The NOC’s goal is to keep services
          rail authorities,such as the Office of  facility,which is used severaltimes a    registering atrack forceof412kN,         running, which includes deploying
          Rail andRoad and the Department for     day. TOPS knows the location of every    which is well overNetwork Rail’s limit   ‘Thunderbird’ rescue locos when
          Transport. This enables local teams to  main line registered item of traction    of 350kN. The train wasstopped, the      necessary –such as on April25when
          getonwith service recovery without      and rollingstock but, forexample, an     driver advised to proceed at 20mph       No. 57308 wassummoned to the aid
          taking on the sombreprocedural          engineering train mayhave departed       to Witham wherethe service was           of No. 66423, which had failed at
                                                                                           terminated beforerunning empty to        Washwood Heath on the 4V44 Daventry
                                                                                           Colchester sidings forexamination.       to Wentloog. The rescued train is
                                                                                               Earlier that morning, atrack circuit  seen coming off St AndrewsJunction
                                                                                           failure(TCF) near Bethnal Green was      (Birmingham) and heading towards
                                                                                           discoveredinside aplanned possession     BordesleyJunction. TomStobbs
                                                                                           that wasdue to be given up at 04.40.
                                                                                           The engineering work wascompleted        were undertaken. David Wiltshireasked
                                                                                           to plan and Anglia Control advised       if the NOC could help, but given that
                                                                                           of the TCF, not relatedtothe works,      Anglia Control had implemented a
                                                                                           andthe morning peak service to           sound recovery plan, further assistance
                                                                                           Liverpool Street waslooking to be        wasnot required. The NOC investigated
                                                                                           seriouslycompromised.                    howlongthe dropped rail had been
                                                                                               The on-site teams discoveredtwo      thereand found it had been left for
                                                                                           signalling cables had been crushed       three years, graduallywearing through
                                                                                           by alength of rail laid on bearers that  the bearers under the vibration from
                                                                                           had worn away,exposing the cables        passing trains.
                                                                                           to the direct weight of the rail wearing     This demonstrated what the NOC
                                                                                           through the insulation. Anglia Control   is about, with local teams resolving
                                                                                           reduced MTRCrossrailservicestosix        the immediate problems with train
          The ‘Putting passengers first’ notice in Network Rail’s Quadrant building, Milton  per hour terminating at and starting    operators, while the NOC itself
          Keynes. All photos by PhilMarsh unless stated                                    from Stratfordwhile temporary repairs    investigated the background.           ❯
          22 RAIL EXPRESS September 2019