SCOPE OF WORK CATEGORIES                                                                 COST



           1.  Modernize & Reconfigure Existing Classrooms                                   $    2,750,000

           2.  Existing Building Systems & Toilets                                           $    2,402,000

           3.  Site Utilities                                                                $       976,000

           4.  Classrooms - New Construction                                                 $  11,784,000
           5.  Maker Spaces & Science Labs                                                   $    2,449,000

           6.  Electives                                                                                 --

           7.  Performing Arts Improvements                                                   $   1,248,000
           8.  MPR/Food Service Improvements & Student Dining                                 $   1,092,000

           9.  Physical Education Improvements                                                $   1,547,000

           10. Administration & Staff Support                                                 $   1,073,000

           11. Library & Student Support Services                                             $   1,681,000

           12. Safety, Security, & Campus Control                                             $   2,099,000
           13. District Support Facilities                                                               --

           14. Outdoor Learning Environment & Quads                                           $      356,000

           15. Exterior Play Spaces, Playfields, & Hardcourts                                 $   1,077,000
           16. Next Generation Classroom Flexibility (Furniture)                              $      375,000    The following items are
                                                                                                                excluded from this budget:
           17. Technology Infrastructure                                                      $        32,000   •   Utility hook-up fees & City connection fees
                                                                                                                •   Off-site work and traffic signals
                                                                                                                •   Land acquisition costs
           Total Project Cost ($2016)                                                       $ 30,941,000        •   Hazardous material surveys
                                                                                                                •   Abatement and disposal
                                                                                                                •   Escalation (costs are in 2016$)

        5.21       COST SUMMARY ($2016)                                                                                        Facilities Master Plan  173
                   BECKMAN ES                                                                                              Lodi Unified School District
   167   168   169   170   171   172   173   174   175   176   177