Page 215 - Facilities Master Plan 2016
P. 215
flooding occurs at the hallway floors
• Accessibility issues need to be
addressed
• Concrete in the hallways is buckling and All images taken by LPA.
needs to be repaired and/or replaced
• Carpet at the office needs to be replaced
• Restroom upgrades are needed
• Additional power in classrooms is
needed
• Ventilation is needed at the science lab
• Blinds need to be replaced
• Lockset upgrades are needed
Notes from Maintenance & Operations:
• Replace all portable ramps/stairs
• Interior and exterior painting and flooring
• Common areas (restrooms, libraries,
etc.) need specialized access control
• More custodian storage
4600 Acampo Road, Acampo, CA 95220 • Dumpster enclosures for 4 dumpsters
• Upgrade EMS
EXISTING SITE INFORMATION CONDITION ASSESSMENT • Replace 15 HVAC units
• Replace all plumbing fixtures and bring
Year Built: 1963 Recently Completed Work: restrooms up to ADA compliance
Site Acreage: 8.57 acres • Portables may need siding repaired;
• New asphalt paving Main Bldg may need siding repaired
Student Population (2014-2015): 176 • Some exterior painting • Replace 60% of door hardware
Grade Levels: K-8 • Blocked off table storage at cafeteria walls • Replace all windows
• A few new restroom partitions • Replace perimeter chainlink fence
Total Number of Classrooms: 18 • Re-roof throughout
Number of Portables: 8 • Needs asphalt overlay at parking and
Notes/Comments from School Site: playgrounds
• Need new mop sinks
• Water is on a well; requires frequent testing • Remove 6 trees
and flushing • New irrigation booster pump needed
• During wet winters, water infiltration and/or
5.29 EXISTING CONDITIONS ASSESSMENT Facilities Master Plan 213