SCOPE OF WORK CATEGORIES                                                                 COST



           1.  Modernize & Reconfigure Existing Classrooms                                    $  2,088,000

           2.  Existing Building Systems & Toilets                                            $  1,455,000

           3.  Site Utilities                                                                 $  1,321,000

           4.  Classrooms - New Construction                                                  $     394,000
           5.  Maker Spaces & Science Labs                                                    $     650,000

           6.  Electives                                                                                 --

           7.  Performing Arts Improvements                                                   $     998,000
           8.  MPR/Food Service Improvements & Student Dining                                 $  1,404,000

           9.  Physical Education Improvements                                                $  1,241,000

           10. Administration & Staff Support                                                 $     388,000

           11. Library & Student Support Services                                             $     843,000

           12. Safety, Security, & Campus Control                                             $  1,901,000
           13. District Support Facilities                                                               --

           14. Outdoor Learning Environment & Quads                                           $     238,000

           15. Exterior Play Spaces, Playfields, & Hardcourts                                 $  1,496,000
           16. Next Generation Classroom Flexibility (Furniture)                              $     210,000     The following items are
                                                                                                                excluded from this budget:
           17. Technology Infrastructure                                                      $       32,000    •   Utility hook-up fees & City connection fees
                                                                                                                •   Off-site work and traffic signals
                                                                                                                •   Land acquisition costs
           Total Project Cost ($2016)                                                       $ 14,659,000        •   Hazardous material surveys
                                                                                                                •   Abatement and disposal
                                                                                                                •   Escalation (costs are in 2016$)

        5.29       COST SUMMARY ($2016)                                                                                        Facilities Master Plan  216
                   HOUSTON SCHOOL                                                                                          Lodi Unified School District
   213   214   215   216   217   218   219   220   221   222   223