Page 257 - Facilities Master Plan 2016
P. 257
SCOPE OF WORK CATEGORIES COST
1. Modernize & Reconfigure Existing Classrooms $ 2,942,000
2. Existing Building Systems & Toilets $ 2,528,000
3. Site Utilities $ 1,592,000
4. Classrooms - New Construction $ 3,971,000
5. Maker Spaces & Science Labs $ 2,225,000
6. Electives --
7. Performing Arts Improvements $ 998,000
8. MPR/Food Service Improvements & Student Dining $ 1,029,000
9. Physical Education Improvements $ 1,411,000
10. Administration & Staff Support $ 626,000
11. Library & Student Support Services $ 1,619,000
12. Safety, Security, & Campus Control $ 1,214,000
13. District Support Facilities --
14. Outdoor Learning Environment & Quads $ 629,000
15. Exterior Play Spaces, Playfields, & Hardcourts $ 1,984,000
16. Next Generation Classroom Flexibility (Furniture) $ 345,000 The following items are
excluded from this budget:
17. Technology Infrastructure -- • Utility hook-up fees & City connection fees
• Off-site work and traffic signals
• Land acquisition costs
Total Project Cost ($2016) $ 23,113,000 • Hazardous material surveys
• Abatement and disposal
• Escalation (costs are in 2016$)
5.35 COST SUMMARY ($2016) Facilities Master Plan 252
JULIA MORGAN ES Lodi Unified School District