SCOPE OF WORK CATEGORIES                                                                 COST



           1.  Modernize & Reconfigure Existing Classrooms                                   $    2,081,000

           2.  Existing Building Systems & Toilets                                           $    1,148,000

           3.  Site Utilities                                                                $    1,202,000

           4.  Classrooms - New Construction                                                 $  12,268,000
           5.  Maker Spaces & Science Labs                                                      $  931,000

           6.  Electives                                                                     $    2,379,000

           7.  Performing Arts Improvements                                                  $    2,101,000
           8.  MPR/Food Service Improvements & Student Dining                                $    1,861,000

           9.  Physical Education Improvements                                               $    9,188,000

           10. Administration & Staff Support                                                $    1,799,000

           11. Library & Student Support Services                                            $    4,216,000

           12. Safety, Security, & Campus Control                                            $    3,426,000
           13. District Support Facilities                                                               --

           14. Outdoor Learning Environment & Quads                                          $       650,000

           15. Exterior Play Spaces, Playfields, & Hardcourts                                $    1,898,000
           16. Next Generation Classroom Flexibility (Furniture)                             $       225,000    The following items are
                                                                                                                excluded from this budget:
           17. Technology Infrastructure                                                     $         32,000   •   Utility hook-up fees & City connection fees
                                                                                                                •   Off-site work and traffic signals
                                                                                                                •   Land acquisition costs
           Total Project Cost ($2016)                                                       $ 45,405,000        •   Hazardous material surveys
                                                                                                                •   Abatement and disposal
                                                                                                                •   Escalation (costs are in 2016$)

        5.56       COST SUMMARY ($2016)                                                                                        Facilities Master Plan  378