SCOPE OF WORK CATEGORIES                                                                 COST



           1.  Modernize & Reconfigure Existing Classrooms                                   $       870,000

           2.  Existing Building Systems & Toilets                                                       --

           3.  Site Utilities                                                                $    1,826,000

           4.  Classrooms - New Construction                                                 $  50,661,000
           5.  Maker Spaces & Science Labs                                                   $  16,045,000

           6.  Electives                                                                     $  25,775,000

           7.  Performing Arts Improvements                                                  $    8,367,000
           8.  MPR/Food Service Improvements & Student Dining                                $  10,540,000

           9.  Physical Education Improvements                                               $  15,319,000

           10. Administration & Staff Support                                                $    5,312,000

           11. Library & Student Support Services                                            $    6,985,000

           12. Safety, Security, & Campus Control                                            $    9,865,000
           13. District Support Facilities                                                   $    2,016,000

           14. Outdoor Learning Environment & Quads                                          $    1,463,000

           15. Exterior Play Spaces, Playfields, & Hardcourts                                $  15,068,000
           16. Next Generation Classroom Flexibility (Furniture)                                         --     The following items are
                                                                                                                excluded from this budget:
           17. Technology Infrastructure                                                                 --     •   Utility hook-up fees & City connection fees
                                                                                                                •   Off-site work and traffic signals
                                                                                                                •   Land acquisition costs
           Total Project Cost ($2016)                                                      $ 170,112,000        •   Hazardous material surveys
                                                                                                                •   Abatement and disposal
                                                                                                                •   Escalation (costs are in 2016$)

        5.58       COST SUMMARY ($2016)                                                                                        Facilities Master Plan  396
                   LODI HS                                                                                                 Lodi Unified School District
   411   412   413   414   415   416   417   418   419   420   421