Lodi Unified School District
                                                                                Facilities Master Plan - Total Program Cost
                                                                                Opinion of Probable Cost                                   April 19, 2016
                                                                                                           INTRODUCTION



                                                                                The information provided by the District is considered to be budgetary for estimating purposes, and a 10% design
                                                                                contingency has been included. The following items are excluded from this budget:
                              Lodi Unified School District                      The following items excluded from scope of work:
                        Facilities Master Plan - Total Program Cost               1 Utility hook-up fees & City connection fees.
                                      Lodi, CA                                    2 Offsite work and traffic signals.
                                                                                  3 Land acquisition costs.
                                                                                  4 Hazardous material surveys, abatement, and disposal.
                                                                                  5 Escalation (Costs are in 2016$ calculated to the end of the year).

                                                                                Each of the unit costs includes the following mark-ups:
                                                                                  A General Contractor GC, OH&P  15.00%
                               Opinion of Probable Cost                           B Bonds & Insurance       2.00%
                                    April 19, 2016                                C Design/Phasing Contingency  10.00%
                                                                                At the category summary level, soft costs are added to each scope portion. Soft costs include the following:
                                                                                  A AE Design Fee          10.00%
                                                                                  B DSA Plan Check Fee      0.75%
                                                                                  C Printing/Advertising    0.05%
                                                                                  E Test/Survey             1.25%
                                                                                  F Inspection              1.25%
                                                                                  G Project Management Fees  5.00%
                                                                                  H Project/Construction Contingency  5.00%
                                                                                   I Relocation Costs       0.80%
                                                                                  J Labor Compliance        0.25%
                                                                                  K Builders Risk Insurance  0.80%
                                                                                  L Legal                   0.03%
                                                                                  M Comissioning            0.08%
                                                                                  N FF&E (Other than Classroom)  4.00%
                                                                                  O Other Miscellaneous Consultants  4.00%
                                                                                   Total Soft Cost Multiplier  33.26%

                                                                                We recommend the client review this statement, and that any interpretations contrary to those intended by the design
                                                                                documents be fully addressed. The statement is based on a detailed measurement of quantities when possible, and
                                 Prepared for LPA, Inc.                         reasonable allowance for items not clearly defined in the documents.
                                                                                The statement reflects probable construction costs obtainable in the currently stable bidding market. The present estimate
                                                                                is a based on a minimum of four to five competitive bids from general contractors,  bidding to a minimum of  four (4)
                                                                                subcontractors per trade. This statement is a detemination of current market value for the construction of the project, not a
                                                                                prediction of low bid. Experience indicates that a fewer number of bidders may result in higher bid amount, and more
                      130 VANTIS, SUITE 110 • ALISO VIEJO • CALIFORNIA • 92656  bidders may result in a lower bid result. It is our understanding that projects will be procured through a traditional
                          PHONE:  949-900-0440  •  FAX:  949-900-0450           competitive design-bid-build basis.



         6.2       APPENDIX                                                                                                    Facilities Master Plan  475
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District