Page 509 - Facilities Master Plan 2016
P. 509

Lodi Unified School District                                            Lodi Unified School District
          Facilities Master Plan - Total Program Cost                             Ansel Adams Elementary School
                                                                                  Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                                Opinion of Probable Cost                                   19-Apr-16
          Project Cost Summary (2016$)
          19-Apr-16                                                                             Project Cost Summary (2016$) - Ansel Adams Elementary School
                                                                                                                              Construction Costs   Total Project
                                                     49        Total Project      Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                 Manlio Silva Growth              01 Modernize & Reconfigure Aging Classrooms     $                       -  $                             -
          Category                                   K-8         Cost (2016$)      Not included in this Facilities Needs Assessment
                                                                                    -                              73,696,000  02 Existing Building Systems & Toilets  $              181,000 $                    241,000
          01 Modernize & Reconfigure Aging Classrooms
                                                                                   2f Energy-efficient building systems and controls (EMS   Upgrade to existing
                                                                                    -                              58,718,000  system, per sf of Bldg)             50,155 sf  $                 3.60 $            181,000  EMS (50%).
          02 Existing Building Systems & Toilets
                                                                    2,225,000                            50,162,000
          03 Site Utilities                                                       03 Site Utilities                               $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
                                                                  37,776,000                        439,292,000
          04 Classrooms New Construction
                                                                                  04 Classrooms New Construction                  $           6,667,000 $                 8,867,000
                                                                    3,729,000                        101,145,000
          05 Maker Spaces & Science Labs
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                    2,112,000                            95,807,000  4a.2 New Pre-School, DK & Kindergarten Building                2,970 sf  $             395.00 $         1,173,000
          06 Electives
                                                                                    4a.4 Sitework & Site Improvements                2,970 sf  $               38.00 $            113,000
                                                                    1,700,000                            57,736,000  4b New Construction - Classrooms
          07 Performing Arts Improvements                                           4b.1 Remove Portable Classrooms                        8 ea  $       11,000.00 $              88,000
                                                                  10,741,000                            76,098,000  4b.4 New Elementary Classroom Building (1-story)             10,800 sf  $             404.00 $         4,363,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining        4b.10 Sitework & Site Improvements             10,800 sf  $               38.00 $            410,000
                                                                                   4d Student Collaboration Lab
                                                                    2,998,000                        129,101,000   4d.1 New Student Collaboration Lab, 1- Story                1,200 sf  $             395.00 $            474,000
          09 Physical Education Improvements
                                                                                    4d.2 Sitework & Site Improvements                1,200 sf  $               38.00 $              46,000
                                                                    2,897,000                            53,143,000
          10 Administration & Staff Support
                                                                                  05 Maker Spaces & Science Labs                  $           1,673,000 $                 2,225,000
                                                                    5,728,000                            90,170,000  5a ES Science / Creativity Labs
          11 Library & Student Support Services                                     5a.6 New ES Science / Creativity Labs Building                 3,500 sf  $             440.00 $         1,540,000
                                                                                    5a.7 Sitework & Site Improvements                3,500 sf  $               38.00 $            133,000
                                                                    2,667,000                        100,511,000
          12 Safety, Security & Campus Control
                                                                                  06 Electives                                    $                       -  $                             -
                                                                                    -                              27,308,000
          13 District Support Facilities                                           Not included in this Facilities Needs Assessment
                                                                        612,000                            16,034,000
          14 Outdoor Learning Environments & Quads                                07 Performing Arts Improvements                 $              750,000 $                    998,000
                                                                                   7a Music Lab
                                                                    2,645,000                            92,195,000  7a.4 New Music Lab                1,540 sf  $             449.00 $            691,000
          15 Exterior Play Spaces, Playfields & Hardcourts
                                                                                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
                                                                                   7b Music/Drama/Dance and Support Spaces
                                                                                    -                              12,467,000
          16 Next Generation Classroom Flexibility (Furniture)                     Not included in this Facilities Needs Assessment
                                                                                    -                                   576,000
          17 Technology Infrastructure                                            08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          Total Project Cost (2016$)                              75,830,000                     1,474,159,000
          Prepared by: LPA, Inc. / Cumming                                       Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  480
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   504   505   506   507   508   509   510   511   512   513   514