Lodi Unified School District                                            Lodi Unified School District
          Ansel Adams Elementary School                                           Ansel Adams Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Ansel Adams Elementary School           Project Cost Summary (2016$) - Ansel Adams Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          09 Physical Education Improvements               $              933,000 $                 1,241,000  16 Next Generation Classroom Flexibility (Furniture)  $              405,000 $                    405,000
            9c PE/Fitness Labs                                                     16a Flexible furniture (Per Classroom, Direct Cost)                     27 ea  $       15,000.00 $            405,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
                                                                                  17 Technology Infrastructure                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          10 Administration & Staff Support                $                       -  $                             -
            Not included in this Facilities Needs Assessment
                                                                                  Total Construction/Project Cost (2016$)         $         12,434,000  $16,405,000
          11 Library & Student Support Services            $                       -  $                             -
            Not included in this Facilities Needs Assessment                      The following items are excluded from this budget:
                                                                                  Utility hook-up fees & City connection fees.
                                                                                  Offsite work and traffic signals.
          12 Safety, Security & Campus Control             $              411,000 $                    547,000  Land acquisition costs.
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  Hazardous material surveys, abatement, and disposal.
            12b.1 New Parking Lot              18,000 sf  $               16.00 $            288,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12b.11 New concrete walkways                2,000 sf  $               15.00 $              30,000
            12e Safety locks at classroom doors                     50 ea  $             449.00 $              22,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.1 Chain Link Perimeter Fencing                   360 lf  $               99.00 $              36,000
            12h.4 Rolling Chain Link Gate                        1 ea  $       25,200.00 $              25,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                 79,000 $                    105,000
            14b Learning Courts
            14b.2 New Learning Court                3,600 sf  $               21.85 $              79,000

           15 Exterior Play Spaces, Playfields & Hardcourts  $           1,335,000 $                 1,776,000
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                2,025 sf  $               20.00 $              41,000
            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                5,850 sf  $               20.00 $            117,000
            15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00 $              63,000
            15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00 $              18,000
            15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            15b.5 Resurface & Repair Hardcourts             14,000 sf  $                 5.00 $              70,000
            15b.6 New Hardcourts               46,450 sf  $               11.00 $            511,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33 $              25,000
            15c Playfields
                                                                  10 year old field -
            15c.1 Repair Playfields           110,400 sf  $                 1.50 $            166,000  partial repair


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  481
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   505   506   507   508   509   510   511   512   513   514   515