Page 513 - Facilities Master Plan 2016
P. 513

Lodi Unified School District                                            Lodi Unified School District
          Lois E. Borchardt Elementary School                                     Lois E. Borchardt Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                       Project Cost Summary (2016$) - Lois E. Borchardt Elementary School      Project Cost Summary (2016$) - Lois E. Borchardt Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $              388,000 $                    516,000  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              410,000 $                    545,000
            1b Replacement or repair of walls                                      8a Elementary/Middle School multipurpose rooms
            1b.1 Replace walls                    4,620 sf  $               39.50 $            182,000  8a.3 Reconfigure Multipurpose Room                   800 sf  $             296.00 $            237,000  stage
            1e Replacement or repair of floors                                     8d New Lunch Shelters                  2,400 sf  $               72.00 $            173,000
            1e.1 Replace floors                   4,620 sf  $               14.40 $              67,000
            1f Replacement or repair of ceilings
            1f.1 Replace ceilings                 4,620 sf  $               27.00 $            125,000  09 Physical Education Improvements  $              933,000 $                 1,241,000
            1g Patch & Paint Interior/Exterior                                     9c PE/Fitness Labs
            1g.1 Patch & paint interior                4,620 sf  $                 3.10 $              14,000  9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000
                                                                                    9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
          02 Existing Building Systems & Toilets           $              460,000 $                    612,000
            2e Replace aging plumbing, upgrade and/or expand                      10 Administration & Staff Support               $              176,000 $                    234,000
            restroom facilities                                                    10a Expanded, reorganized or relocated administration
            2e.3 New Restroom                        750 sf  $             556.00 $            417,000  spaces
            2e.4 Sitework & Site Improvements                   750 sf  $               57.00 $              43,000  10a.3 Reconfigure Administration                   750 sf  $             235.00 $            176,000
          03 Site Utilities                                $                       -  $                             -  11 Library & Student Support Services  $           1,048,000 $                 1,394,000
            Not included in this Facilities Needs Assessment                       11a Elementary School Library/Innovation Lab
                                                                                    11a.2 New Library/Innovation Lab Building                1,320 sf  $             406.00 $            536,000
                                                                                    11a.5 Sitework & Site Improvements                1,320 sf  $               38.00 $              50,000
          04 Classrooms New Construction                   $           4,161,000 $                 5,534,000  11d Learning Center
                                                                                    11d.4 Reconfigure Learning Center                1,950 sf  $             237.00 $            462,000
            4a New Construction - Pre-School, DK & Kindergarten                                             .
            4a.2 New Pre-School, DK & Kindergarten Building                1,485 sf  $             395.00 $            587,000  12 Safety, Security & Campus Control  $              882,000 $                 1,173,000
            4a.4 Sitework & Site Improvements                1,485 sf  $               38.00 $              56,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
            4b New Construction - Classrooms                                        12b.1 New Parking Lot              16,800 sf  $               16.00 $            269,000
            4b.1 Remove Portable Classrooms                        2 ea  $       11,000.00 $              22,000  12b.5 New Drop-off Area             10,800 sf  $               18.00 $            194,000
                                                                                    12b.11 New concrete walkways                2,400 sf  $               15.00 $              36,000
            4b.4 New Elementary Classroom Building (1-story)                7,392 sf  $             404.00 $         2,986,000  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            4b.10 Sitework & Site Improvements                7,392 sf  $               38.00 $            281,000  12e Safety locks at classroom doors                     45 ea  $             449.00 $              20,000
            4d Student Collaboration Lab                                           12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            4d.1 New Student Collaboration Lab, 1- Story                   528 sf  $             395.00 $            209,000  12g Marquee Sign                        1 ea  $       10,000.00 $              10,000
            4d.2 Sitework & Site Improvements                   528 sf  $               38.00 $              20,000  12h Fencing with controlled campus entrances
                                                                                    12h.2 Decorative Metal Fencing & Gates                   830 lf  $             252.00 $            209,000
                                                                                    12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
          05 Maker Spaces & Science Labs                   $              737,000 $                    980,000  12i Fire safety equipment, fire alarms and emergency lighting
            5a ES Science / Creativity Labs                                         12i.1 Fire Alarm System                2,700 sf  $                 5.40 $              15,000
            5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00 $            678,000  12i.2 Emergency Lighting                2,700 sf  $                 1.40 $                 4,000
            5a.7 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  12j New public address/emergency communication
                                                                                   systems                                2,700 sf  $                 7.60 $              21,000
                                                                                   12k Intrusion alarms                   2,700 sf  $                 1.80 $                 5,000
          06 Electives                                     $                       -  $                             -
            Not included in this Facilities Needs Assessment
                                                                                  13 District Support Facilities                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          07 Performing Arts Improvements                  $              750,000 $                    998,000
            7a Music Lab
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming

         6.2       APPENDIX                                                                                                    Facilities Master Plan  484
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District