Page 518 - Facilities Master Plan 2016
P. 518

Lodi Unified School District                                            Lodi Unified School District
          Creekside Elementary School                                             Davis Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Creekside Elementary School              Project Cost Summary (2016$) - Davis Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          Total Construction/Project Cost (2016$)          $         20,970,000  $27,801,000  01 Modernize & Reconfigure Aging Classrooms  $           2,878,000 $                 3,828,000
                                                                                   1a Structural Strengthening
                                                                                    1a.2 Wall strengthening             16,320 sf  $               13.50 $            220,000
          The following items are excluded from this budget:                       1b Replacement or repair of walls
           Utility hook-up fees & City connection fees.                             1b.1 Replace walls                 16,320 sf  $               39.50 $            645,000
           Offsite work and traffic signals.                                       1c Replacement or repair of windows
           Land acquisition costs.                                                  1c.1 Replace windows               16,320 sf  $               18.00 $            294,000
           Hazardous material surveys, abatement, and disposal.                    1d Replacement or repair of doors (other than safety locks
           Escalation (Costs are in 2016$ calculated to the end of the year).      @ classroom doors)
                                                                                    1d.1 Replace doors & hardware             16,320 sf  $               13.50 $            220,000
                                                                                   1e Replacement or repair of floors
                                                                                    1e.1 Replace floors                16,320 sf  $               14.40 $            235,000
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.1 Replace ceilings              16,320 sf  $               27.00 $            441,000
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior             16,320 sf  $                 3.10 $              51,000
                                                                                    1g.2 Patch & paint exterior             16,320 sf  $                 4.50 $              73,000
                                                                                   1o Replace Existing Roofing             28,195 sf  $               20.93 $            590,000
                                                                                   1p Repair Existing Covered Walkways / Hallways                8,380 sf  $               13.00 $            109,000
                                                                                  02 Existing Building Systems & Toilets          $           1,513,000 $                 2,012,000
                                                                                   2a HVAC system upgrades             16,320 sf  $               29.00 $            473,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             16,320 sf  $               15.00 $            245,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            16,320 sf  $                 9.00 $            147,000
                                                                                   2d Plumbing system upgrades             16,320 sf  $               11.00 $            180,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.2 Reconfigure Existing Restroom                1,575 sf  $             222.00 $            350,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             16,320 sf  $                 7.20 $            118,000
                                                                                  03 Site Utilities                               $           1,830,000 $                 2,434,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           583,704 sf  $                 0.28 $            163,000
                                                                                   3b Updated sewer service lines           583,704 sf  $                 0.49 $            286,000
                                                                                   3c Updated water service lines           583,704 sf  $                 0.63 $            368,000
                                                                                   3d Updated electrical mains and distribution           583,704 sf  $                 0.90 $            525,000
                                                                                   3e Updated storm drainage system           583,704 sf  $                 0.54 $            315,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     172,500.00 $            173,000
                                                                                  04 Classrooms New Construction                  $           4,436,000 $                 5,900,000
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                4,455 sf  $             395.00 $         1,760,000
                                                                                    4a.4 Sitework & Site Improvements                4,455 sf  $               38.00 $            169,000



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  489
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District