Lodi Unified School District                                            Lodi Unified School District
          Heritage Primary Elementary School                                      Heritage Primary Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                       Project Cost Summary (2016$) - Heritage Primary Elementary School       Project Cost Summary (2016$) - Heritage Primary Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          05 Maker Spaces & Science Labs                   $           1,472,000 $                 1,958,000  12 Safety, Security & Campus Control  $           1,293,000 $                 1,720,000
            5a ES Science / Creativity Labs                                        12b Safety improvements to and/or new parent/bus drop-off areas and parking
            5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00 $         1,355,000  12b.1 New Parking Lot             17,000 sf  $               16.00 $            272,000
            5a.7 Sitework & Site Improvements                3,080 sf  $               38.00 $            117,000  12b.3 Entry Plaza                1,000 sf  $               26.00 $              26,000
                                                                                    12b.5 New Drop-off Area                3,200 sf  $               18.00 $              58,000
                                                                                    12b.9 Repair existing Parking Lot                6,400 sf  $                 6.30 $              40,000
          06 Electives                                     $                       -  $                             -  12b.11 New concrete walkways                1,500 sf  $               15.00 $              23,000
            Not included in this Facilities Needs Assessment                       12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
                                                                                   12e Safety locks at classroom doors                     30 ea  $             449.00 $              13,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
          07 Performing Arts Improvements                  $              750,000 $                    998,000  12g Marquee Sign                        1 ea  $       10,000.00 $              10,000
            7a Music Lab                                                           12h Fencing with controlled campus entrances
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000  12h.1 Chain Link Perimeter Fencing                   350 lf  $               99.00 $              35,000
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  12h.2 Decorative Metal Fencing & Gates                   900 lf  $             252.00 $            227,000
                                                                                    12h.3 Rolling Decorative Metal Gate                        2 ea  $       27,000.00 $              54,000
                                                                                    12h.4 Rolling Chain Link Gate                        1 ea  $       25,200.00 $              25,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,440,000 $                 1,915,000  12i Fire safety equipment, fire alarms and emergency lighting
            8a Elementary/Middle School multipurpose rooms                          12i.1 Fire Alarm System             26,966 sf  $                 5.40 $            146,000
            8a.2 Modernize Multipurpose Room                2,400 sf  $               99.00 $            238,000  12i.2 Emergency Lighting             26,966 sf  $                 1.40 $              38,000
            8a.3 Reconfigure Multipurpose Room                   800 sf  $             296.00 $            237,000  12j New public address/emergency communication
            8c Food service areas                                                  systems                             26,966 sf  $                 7.60 $            205,000
            8c.4 New Food Service                 1,200 sf  $             584.00 $            701,000  12k Intrusion alarms             26,966 sf  $                 1.80 $              49,000
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
            8c.9 Sitework & Site Improvements                1,200 sf  $               38.00 $              46,000
            8d New Lunch Shelters                 2,400 sf  $               72.00 $            173,000  13 District Support Facilities  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          09 Physical Education Improvements               $              933,000 $                 1,241,000
            9c PE/Fitness Labs                                                    14 Outdoor Learning Environments & Quads        $              203,000 $                    270,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  14a Main Student Quad
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000  14a.2 New Main Student Quad                7,200 sf  $               23.00 $            166,000
                                                                                   14b Learning Courts
                                                                                    14b.2 New Learning Court                1,600 sf  $               23.00 $              37,000
          10 Administration & Staff Support                $              636,000 $                    846,000
            10a Expanded, reorganized or relocated administration
            spaces                                                                15 Exterior Play Spaces, Playfields & Hardcourts  $              429,000 $                    571,000
            10a.3 Reconfigure Administration                2,100 sf  $             235.00 $            494,000  15a Kindergarten Play Yard
            10b Staff Collaboration/Work Rooms                                      15a.1 New Rubberized Surface Play Area                   900 sf  $               20.00 $              18,000
            10b.2 Modernize Staff Collaboration/Work Rooms                1,200 sf  $             118.00 $            142,000  15a.3 Shade Structure                1,200 sf  $               90.00 $            108,000
                                                                                   15b PE Play Yard & Hardcourts
                                                                                    15a.1 New Rubberized Surface Play Area                2,400 sf  $               20.00 $              48,000
          11 Library & Student Support Services            $           2,285,000 $                 3,039,000  15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00 $              18,000
            11a Elementary School Library/Innovation Lab                            15b.7 Slurry Coat & Stripe Existing Hardcourts             38,400 sf  $                 3.00 $            115,000
            11a.2 New Library/Innovation Lab Building                4,290 sf  $             406.00 $         1,742,000  15c Playfields
            11a.5 Sitework & Site Improvements                4,290 sf  $               38.00 $            163,000  15c.1 Repair Playfields             40,800 sf  $                 3.00 $            122,000
            11d Learning Center
            11d.3 Modernize Learning Center                   500 sf  $             119.00 $              60,000
            11d.4 Reconfigure Learning Center                1,350 sf  $             237.00 $            320,000  16 Next Generation Classroom Flexibility (Furniture)  $              255,000 $                    255,000
                                                                                   16a Flexible furniture (Per Classroom, Direct Cost)                     17 ea  $       15,000.00 $            255,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming

         6.2       APPENDIX                                                                                                    Facilities Master Plan  494
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District