Page 528 - Facilities Master Plan 2016
P. 528

Lodi Unified School District                                            Lodi Unified School District
          Lakewood Elementary School                                              Ellerth E. Larson Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Lakewood Elementary School             Project Cost Summary (2016$) - Ellerth E. Larson Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          16 Next Generation Classroom Flexibility (Furniture)  $                240,000 $                    240,000  01 Modernize & Reconfigure Aging Classrooms  $              190,000 $                    253,000
           16a Flexible furniture (Per Classroom, Direct Cost)                     16 ea  $       15,000.00 $             240,000  1b Replacement or repair of walls
                                                                                    1b.1 Replace walls                    1,920 sf  $               39.50 $              76,000
                                                                                   1e Replacement or repair of floors
          17 Technology Infrastructure                    $                   32,000 $                      32,000  1e.1 Replace floors                1,920 sf  $               14.40 $              28,000
            17c MDF and IDF data rooms with environmental control                  1f Replacement or repair of ceilings
           (direct cost only)                             1 ea  $       32,000.00 $               32,000  1f.1 Replace ceilings                1,920 sf  $               27.00 $              52,000
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior                1,920 sf  $                 3.10 $                 6,000
          Total Construction/Project Cost (2016$)         $           25,338,000  $33,610,000
                                                                                  02 Existing Building Systems & Toilets          $              460,000 $                    612,000
          The following items are excluded from this budget:                       2e Replace aging plumbing, upgrade and/or expand
           Utility hook-up fees & City connection fees.                            restroom facilities
           Offsite work and traffic signals.                                        2e.3 New Restroom                        750 sf  $             556.00 $            417,000
           Land acquisition costs.                                                  2e.4 Sitework & Site Improvements                   750 sf  $               57.00 $              43,000
           Hazardous material surveys, abatement, and disposal.
           Escalation (Costs are in 2016$ calculated to the end of the year).
                                                                                  03 Site Utilities                               $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
                                                                                  04 Classrooms New Construction                  $           5,082,000 $                 6,759,000
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                7,425 sf  $             395.00 $         2,933,000
                                                                                    4a.4 Sitework & Site Improvements                7,425 sf  $               38.00 $            282,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.4 New Elementary Classroom Building (1-story)                4,224 sf  $             404.00 $         1,706,000
                                                                                    4b.10 Sitework & Site Improvements                4,224 sf  $               38.00 $            161,000
                                                                                  05 Maker Spaces & Science Labs                  $              737,000 $                    980,000
                                                                                   5a ES Science / Creativity Labs
                                                                                    5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00 $            678,000
                                                                                    5a.7 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
                                                                                  06 Electives                                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment

                                                                                  07 Performing Arts Improvements                 $              750,000 $                    998,000
                                                                                   7a Music Lab
                                                                                    7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000
                                                                                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000





         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  499
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District