Page 529 - Facilities Master Plan 2016
P. 529

Lodi Unified School District                                            Lodi Unified School District
          Ellerth E. Larson Elementary School                                     Ellerth E. Larson Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                        Project Cost Summary (2016$) - Ellerth E. Larson Elementary School     Project Cost Summary (2016$) - Ellerth E. Larson Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              410,000 $                    545,000  15 Exterior Play Spaces, Playfields & Hardcourts  $              772,000 $                 1,027,000
            8a Elementary/Middle School multipurpose rooms                         15a Kindergarten Play Yard
            8a.3 Reconfigure Multipurpose Room                   800 sf  $             296.00 $            237,000  stage  15a.1 New Rubberized Surface Play Area                3,200 sf  $               20.00 $              64,000
            8d New Lunch Shelters                 2,400 sf  $               72.00 $            173,000  15a.2 Kindergarten Play Apparatus                        1 ea  $       63,000.00 $              63,000
                                                                                    15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
                                                                                    15a.6 New Hardcourts                  8,000 sf  $               11.00 $              88,000
          09 Physical Education Improvements               $              933,000 $                 1,241,000  15b PE Play Yard & Hardcourts
            9c PE/Fitness Labs                                                      15a.1 New Rubberized Surface Play Area                6,600 sf  $               20.00 $            132,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00 $              63,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000  15b.6 New Hardcourts             20,800 sf  $               11.00 $            229,000
                                                                                    15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33 $              25,000
          10 Administration & Staff Support                $              176,000 $                    234,000
            10a Expanded, reorganized or relocated administration                 16 Next Generation Classroom Flexibility (Furniture)  $              248,000 $                    248,000
            spaces                                                                 16a Flexible furniture (Per Classroom, Direct Cost)                     33 ea  $         7,500.00 $            248,000
            10a.3 Reconfigure Administration                   750 sf  $             235.00 $            176,000
                                                                                  17 Technology Infrastructure                    $                       -  $                             -
          11 Library & Student Support Services            $              462,000 $                    614,000  Not included in this Facilities Needs Assessment
            11d Learning Center
            11d.4 Reconfigure Learning Center                1,950 sf  $             237.00 $            462,000
                                                                                  Total Construction/Project Cost (2016$)         $         11,259,000  $14,892,000
          12 Safety, Security & Campus Control             $              956,000 $                 1,271,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  The following items are excluded from this budget:
            12b.1 New Parking Lot              16,800 sf  $               16.00 $            269,000  Utility hook-up fees & City connection fees.
            12b.5 New Drop-off Area             10,800 sf  $               18.00 $            194,000  Offsite work and traffic signals.
            12b.11 New concrete walkways                2,400 sf  $               15.00 $              36,000  Land acquisition costs.
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  Hazardous material surveys, abatement, and disposal.
            12e Safety locks at classroom doors                     50 ea  $             449.00 $              22,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   785 lf  $             252.00 $            198,000
            12h.3 Rolling Decorative Metal Gate                        3 ea  $       27,000.00 $              81,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                4,620 sf  $                 5.40 $              25,000
            12i.2 Emergency Lighting                4,620 sf  $                 1.40 $                 6,000
            12j New public address/emergency communication
            systems                               4,620 sf  $                 7.60 $              35,000
            12k Intrusion alarms                  4,620 sf  $                 1.80 $                 8,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                 83,000 $                    110,000
            14b Learning Courts
            14b.2 New Learning Court                3,600 sf  $               23.00 $              83,000



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  500
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District