Lodi Unified School District                                            Lodi Unified School District
          Live Oak Elementary School                                              Live Oak Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Live Oak Elementary School              Project Cost Summary (2016$) - Live Oak Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          12 Safety, Security & Campus Control             $           1,324,000 $                 1,761,000  17 Technology Infrastructure  $                 32,000 $                      32,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking   17c MDF and IDF data rooms with environmental control
            12b.1 New Parking Lot              20,800 sf  $               16.00 $            333,000  (direct cost only)                         1 ea  $       32,000.00 $              32,000
            12b.3 Entry Plaza                     1,600 sf  $               26.00 $              42,000
            12b.5 New Drop-off Area             15,800 sf  $               18.00 $            284,000
            12b.11 New concrete walkways                2,800 sf  $               15.00 $              42,000  Total Construction/Project Cost (2016$)  $         18,881,000  $25,064,000
            12d Exterior lighting to ensure student safety                        1 ls  $       60,000.00 $              60,000
            12e Safety locks at classroom doors                     20 ea  $             449.00 $                 9,000
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000  The following items are excluded from this budget:
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000  Utility hook-up fees & City connection fees.
            12h Fencing with controlled campus entrances                          Offsite work and traffic signals.
            12h.2 Decorative Metal Fencing & Gates                   900 lf  $             252.00 $            227,000  Land acquisition costs.
            12h.3 Rolling Decorative Metal Gate                        2 ea  $       27,000.00 $              54,000  Hazardous material surveys, abatement, and disposal.
            12i Fire safety equipment, fire alarms and emergency lighting         Escalation (Costs are in 2016$ calculated to the end of the year).
            12i.1 Fire Alarm System             14,256 sf  $                 5.40 $              77,000
            12i.2 Emergency Lighting             14,256 sf  $                 1.40 $              20,000
            12j New public address/emergency communication
            systems                            14,256 sf  $                 7.60 $            108,000
            12k Intrusion alarms               14,256 sf  $                 1.80 $              26,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $              381,000 $                    507,000
            14a Main Student Quad
            14a.2 New Main Student Quad                7,200 sf  $               21.85 $            157,000
            14b Learning Courts
            14b.2 New Learning Court             10,800 sf  $               20.70 $            224,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $           1,044,000 $                 1,389,000
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                1,200 sf  $               20.00 $              24,000
            15a.2 Relocate Kindergarten Play Apparatus                        1 ea  $       18,000.00 $              18,000
            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            15a.6 New Hardcourts                  3,500 sf  $               11.00 $              39,000
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                4,500 sf  $               20.00 $              90,000
            15b.6 New Hardcourts               46,100 sf  $               11.00 $            507,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33 $              25,000
            15c Playfields
            15c.1 Repair Playfields             77,600 sf  $                 3.00 $            233,000
           16 Next Generation Classroom Flexibility (Furniture)  $              120,000 $                    120,000
            16a Flexible furniture (Per Classroom, Direct Cost)                        8 ea  $       15,000.00 $            120,000





         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  504
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   528   529   530   531   532   533   534   535   536   537   538