Lodi Unified School District                                            Lodi Unified School District
          Lockeford Elementary School                                             Lockeford Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Lockeford Elementary School              Project Cost Summary (2016$) - Lockeford Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4d Student Collaboration Lab
          01 Modernize & Reconfigure Aging Classrooms      $              867,000 $                 1,153,000  4d.1 New Student Collaboration Lab, 1- Story                2,112 sf  $             395.00 $            834,000
            1b Replacement or repair of walls                                       4d.2 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
            1b.2 Repair walls                     6,630 sf  $               12.60 $              84,000
            1c Replacement or repair of windows
            1c.1 Replace windows                  6,630 sf  $               18.00 $            119,000  05 Maker Spaces & Science Labs  $           1,472,000 $                 1,958,000
            1d Replacement or repair of doors (other than safety locks             5a ES Science / Creativity Labs
            @ classroom doors)                                                      5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00 $         1,355,000
            1d.1 Replace doors & hardware                6,630 sf  $               13.50 $              90,000  5a.7 Sitework & Site Improvements                3,080 sf  $               38.00 $            117,000
            1e Replacement or repair of floors
            1e.1 Replace floors                   6,630 sf  $               14.40 $              95,000
            1f Replacement or repair of ceilings                                  06 Electives                                    $              341,000 $                    454,000
            1f.1 Replace ceilings                 6,630 sf  $               27.00 $            179,000  6a MS/HS Electives
            1g Patch & Paint Interior/Exterior                                      6a.5 Reconfigure MS/HS Electives Building                 1,440 sf  $             237.00 $            341,000
            1g.1 Patch & paint interior                6,630 sf  $                 3.10 $              21,000
            1g.2 Patch & paint exterior                6,630 sf  $                 4.50 $              30,000
            1o Replace Existing Roofing             10,624 sf  $               20.93 $            222,000  07 Performing Arts Improvements  $              750,000 $                    998,000
            1p Repair Existing Covered Walkways / Hallways                2,110 sf  $               13.00 $              27,000  7a Music Lab
                                                                                    7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000
                                                                                    7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
          02 Existing Building Systems & Toilets           $              774,000 $                 1,029,000
            2a HVAC system upgrades                6,630 sf  $               29.00 $            192,000
                                                                                  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                 45,000 $                      60,000
            2b Lighting upgrades - new interior lighting & controls                6,630 sf  $               15.00 $              99,000  8c Food service areas
            2c Electrical upgrades                                                  8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
            2c.1 Upgrade electrical wiring & increase electrical
            outlets                               6,630 sf  $                 9.00 $              60,000
            2d Plumbing system upgrades                6,630 sf  $               11.00 $              73,000  09 Physical Education Improvements  $                       -  $                             -
            2e Replace aging plumbing, upgrade and/or expand                       Not included in this Facilities Needs Assessment
            restroom facilities
            2e.2 Reconfigure Existing Restroom                1,360 sf  $             222.00 $            302,000
            2f Energy-efficient building systems and controls (EMS
            system, per sf of Bldg)                6,630 sf  $                 7.20 $              48,000  10 Administration & Staff Support  $           1,783,000 $                 2,371,000
                                                                                   10a Expanded, reorganized or relocated administration
                                                                                   spaces
                                                                                    10a.4 New Administration                1,900 sf  $             392.00 $            745,000
          03 Site Utilities                                $           1,843,000 $                 2,451,000  10a.5 Sitework & Site Improvements                1,900 sf  $               38.00 $              72,000
            (For entire campus and site)                                           10b Staff Collaboration/Work Rooms
            3a Updated gas service lines           418,176 sf  $                 0.40 $            167,000  10b.3 Reconfigure Staff Collaboration/Work Rooms                   450 sf  $             235.00 $            106,000
            3b Updated sewer service lines           418,176 sf  $                 0.67 $            278,000  10b.4 New Staff Collaboration/Work Rooms                2,000 sf  $             392.00 $            784,000
            3c Updated water service lines           418,176 sf  $                 0.86 $            358,000
            3d Updated electrical mains and distribution           418,176 sf  $                 1.08 $            452,000  10b.5 Sitework & Site Improvements                2,000 sf  $               38.00 $              76,000
            3e Updated storm drainage system           418,176 sf  $                 0.86 $            358,000
            3f Electrical Capacity Upgrades                        1 ls  $     230,000.00 $            230,000
                                                                                  11 Library & Student Support Services           $              838,000 $                 1,115,000
                                                                                   11a Elementary School Library/Innovation Lab
                                                                                    11a.3 Modernize Library/Innovation Lab Building                3,560 sf  $             122.00 $            434,000
          04 Classrooms New Construction                   $           5,225,000 $                 6,949,000  11d Learning Center
            4b New Construction - Classrooms                                        11d.4 Reconfigure Learning Center                1,704 sf  $             237.00 $            404,000
            4b.1 Remove Portable Classrooms                     10 ea  $       11,000.00 $            110,000
            4b.4 New Elementary Classroom Building (1-story)                9,504 sf  $             404.00 $         3,840,000
            4b.10 Sitework & Site Improvements                9,504 sf  $               38.00 $            361,000  12 Safety, Security & Campus Control  $              765,000 $                 1,017,000
                                                                                   12a  Remaining asbestos removal                8,514 sf  $                 4.00 $              34,000
                                                                                   12b Safety improvements to and/or new parent/bus drop-off areas and parking
                                                                                    12b.1 New Parking Lot              20,300 sf  $               16.00 $            325,000
                                                                                    12b.3 Entry Plaza                     3,000 sf  $               26.00 $              78,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  505
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   529   530   531   532   533   534   535   536   537   538   539